Diligence report AI-ready data centers / digital infrastructure Late-stage private; U.S. IPO filing reported in October 2026 2026-10-26

DayOne Data Centers

Investment diligence refresh | 26 October 2026

DayOne shows meaningful scale and capital access, but concentrated customers, opaque economics, and unsettled IPO terms make the reported target difficult to underwrite.

Coverage and disclosure

Public reporting supports scale and financing signals but does not provide audited standalone cash flow, realized unit economics, final IPO terms, or a reliable customer-level operating bridge. Secondary reports conflict on first-half 2026 net loss and reported capacity bookings.

Cover facts

Latest reported financing 01
US$4.5 billion gross proceeds, Series C (June 2026) [CO004, CI006]
First-half 2026 revenue 02
US$512 million [CO010, CI004]
Reported capacity bookings 03
2.3 GW across 10 markets (Light Reading); another report cites more than 1.5 GW [CI002, CU003]
Largest customer concentration 04
69.4% of FY2025 revenue, as reported [CO013]
First-half 2026 net loss 05
US$77.2M-US$81.9M across conflicting secondary reports [CO011, CO012]
Reported IPO valuation 06
Approximately US$20 billion; not an official valuation [CV002, CV004]
IPO timing 07
Possible delay or US$2.5B-US$3B proceeds alternative reported [CO009, CV005]

Company profile

DayOne Data Centers is a Singapore-headquartered developer and operator of hyperscale data centers for cloud, AI, and large-enterprise customers. The reported platform spans Singapore, Johor, and Batam, with additional expansion plans in Finland. Reports describe rapid revenue growth, substantial capacity bookings, and a US$4.5 billion Series C, but customer concentration, conflicting reported losses, and limited disclosure on cash generation and project economics leave the growth and funding profile incompletely underwritten. The reviewed company-facing sources do not identify founders or executives.

Website
dayonedc.com
Headquarters
Singapore
Product
Powered, cooled, interconnected hyperscale colocation capacity for cloud and AI operators, with customers installing their own computing and network equipment.
Customers
Hyperscalers, cloud providers, AI operators, and large enterprises.
Business model
Develops and operates data-center facilities and sells long-term IT-power capacity and colocation services; realized pricing, service mix, and campus-level margins are not disclosed.
Stage
Late-stage private; U.S. IPO filing reported in October 2026.
Funding status
US$4.5 billion gross-proceeds Series C announced in June 2026; more than US$6 billion in equity financing since 2022 is reported.
[CO001, CO002, CO004, CO008, CO009, CO010, CO013, CI001, CI002, CI016, CU001, CU002, CO016]

Executive summary

Top strengths

  • Reported first-half 2026 revenue of US$512 million and capacity bookings across multiple markets indicate substantial operating scale.
  • A US$4.5 billion Series C and more than US$6 billion of reported equity financing provide meaningful capital access.
  • Regional hyperscale and AI data-center demand supports a large opportunity, although delivery depends on power and approvals.

Top risks

  • The largest customer reportedly represented 69.4% of FY2025 revenue, while contract duration and renewal sensitivity remain undisclosed.
  • Conflicting reports put the first-half 2026 net loss at US$77.2 million or US$81.9 million; cash flow, runway, and project returns are not established.
  • IPO timing, offer price, share count, and valuation remain unsettled, so investor returns cannot be calculated.
  • Power availability, permitting, and site-level delivery milestones could constrain a capital-intensive expansion.

Open gaps

  • Reconcile audited standalone statements, first-half loss figures, adjusted EBITDA definitions, cash flow, debt, committed capex, and runway.
  • Obtain final IPO terms, offer price, share count, net-debt bridge, and capital structure before estimating valuation or returns.
  • Verify customer-level revenue and MW concentration, contract duration, renewal terms, and named site deployments.
  • Reconcile booked capacity to energized, billable, and recognized revenue by customer and campus.
  • Obtain site-level power allocation, permits, commissioning milestones, and capex per delivered MW.
  • Identify founders and leadership roles from authoritative company disclosures.

Contents

Chapter 01

01Company Overview

1.1 Identity, model, and operating footprint

DayOne describes a capital-intensive infrastructure model: it develops and operates hyperscale data centers for hyperscalers and large enterprises, rather than selling a software subscription. The company identifies Singapore as its headquarters and presents SIJORI—Singapore, Johor, and Batam—as a connected regional platform. This is a company description, not independent evidence that the network has achieved the claimed operating advantages. Its public narrative traces the business to GDS International and a GDS Holdings spinout; available reports differ in how they describe the timing of the transition to the DayOne name and independence. The sources reviewed do not establish a verified total for customers, employees, or all-time funding. The snapshot therefore distinguishes reported figures from unknown or unreconciled metrics rather than treating a round's gross proceeds as cash on hand.[CO001, CO002, CO003]

Company snapshot and reported metrics
MetricValue / statusPeriod / dateConfidenceGap or qualification
HeadquartersSingaporeCurrent company profileMediumCompany-facing profile; confirm registered and operating entities.
Business modelDevelops and operates hyperscale data centers for hyperscalers and large enterprisesCurrent company descriptionMediumCompany description; customer mix and contract economics are not established here.
Origin / stageGDS International predecessor; private company with a reported US IPO filingOrigin timing varies by report; IPO filing reported 2026-10-05MediumClarify legal spinout, rebrand, and current entity history.
Series CUS$4.5bn gross proceedsClosed June 2026; initial US$2bn tranche reported January 2026MediumRound proceeds are not total funding or cash available.
Total fundingNot reconciledAs of 2026-10-26LowObtain a round-by-round schedule and verify primary documents.
Mezzanine facilityUp to US$1.2bn reportedDecember 2025MediumFacility ceiling is not drawn debt or cash available; outstanding balance and terms are unknown.
IPO proceeds / valuationAbout US$5bn proceeds and a possible US$20bn valuation reported; later possible US$2.5bn–US$3bn offeringOctober 2026 reportingMediumTargets are uncompleted and the possible size change is attributed to Bloomberg sources.
Revenue (not ARR)US$512m; US$151.5m in comparable prior-year periodSix months ended 2026-06-30; six months ended 2025-06-30High for reported revenueReported filing figures; do not annualize or relabel as ARR.
Net lossUS$81.9m (Bloomberg) versus US$77.2m (Startup Fortune)Six months ended 2026-06-30Low pending reconciliationConflicting secondary reporting; verify the filed income statement.
Largest-customer concentration69.4% of revenue in 2025; 69.2% in first half 2026, as reported2025 and six months ended 2026-06-30LowSingle-source disclosure; obtain customer-level revenue and contract terms.
Customer count / headcountNot established in the assigned evidenceCurrentLowRequest dated customer and employee counts, including definitions and entity scope.
Footprint / planned capacityCompany lists Singapore, Johor, Batam, Greater Bangkok, Hong Kong SAR, and Tokyo; Finnish project has up to 560 MW of grid-power potentialCurrent company page; Finnish plan reported 2026-01-22MediumLocations and planned grid power are not equivalent to operational IT load or powered capacity.

Reported company and press figures retain their original metric, period, and uncertainty. Funding announcements and facility ceilings do not establish cash available; IPO targets are not completed valuation; revenue is not ARR; and planned grid power is not operating capacity.

[CO001, CO003, CO004, CO007, CO008, CO010, CO011, CO012, CO013, CO015]

1.2 Leadership, governance, and ownership

Available company-facing pages describe an experienced leadership team but do not identify founders, name an executive roster, or provide board composition. That leaves key-person dependence, governance quality, and control rights unassessed; the absence of names in this assigned source set is not evidence that no such disclosures exist. Reporting identifies Coatue and Hillhouse as the two largest shareholders after leading the Series C, and identifies the Indonesia Investment Authority and Achi Capital Partners as new participants. GDS Holdings remains relevant as former parent: one report says it sold US$385 million of shares back to DayOne in January 2026, while another reports a continuing non-controlling stake. Obtain the current cap table, board roster, voting arrangements, and related-party terms before relying on headline investor names as a proxy for control.[CO003, CO005, CO006, CO016]

Leadership and founder table
Person / areaWhat the assigned sources establishCoverage / dependenceDiligence ask
Founders and originReports describe a GDS International predecessor / spinout, but do not identify individual founders in the reviewed text.Founder-market fit and founder dependence remain unassessed.Obtain incorporation history, founder roles, and current involvement.
Named leadership and boardCompany-facing pages describe an experienced team but provide no named executive or director roster.Functional coverage, succession exposure, and board oversight remain unassessed.Obtain current executive biographies, board roster, committee structure, and succession plan.

This is a disclosure-limit table, not an assertion that the company has no founders, executives, or directors.

[CO003, CO016]

1.3 Financing and public-market status

ISI Markets and Data Center Dynamics report a US$4.5 billion gross Series C close in June 2026; ISI says the round began with a US$2 billion tranche in January. Data Center Knowledge also reports a December 2025 mezzanine facility of up to US$1.2 billion. These are financing announcements and reported facility size, not a reconciled total of capital raised, debt outstanding, or cash available. On October 5, Bloomberg reported that DayOne had filed for a US IPO, while other coverage described a roughly US$5 billion raise and a possible US$20 billion valuation. On October 21, Bloomberg reported that the company was weighing a delay or an offering reduced to US$2.5 billion–US$3 billion. Neither target is a completed transaction or a confirmed valuation. The changing reported timetable is a material execution and market- window uncertainty.[CO004, CO007, CO008, CO009]

Stakeholder or investor map
StakeholderReported roleEconomic or control relevanceDiligence ask
Coatue ManagementExisting investor and Series C leadReported among the two largest shareholders after the roundVerify current ownership, voting rights, and any governance protections.
HillhouseExisting investor and Series C leadReported among the two largest shareholders after the roundVerify current ownership, voting rights, and any governance protections.
Indonesia Investment Authority (INA)New Series C participantSovereign investor; separate joint-venture relationship also reportedSeparate the fund investment from JV economics, rights, and obligations.
Achi Capital PartnersNew Series C participantReported equity participant; stake size is not disclosed in the assigned evidenceConfirm investment vehicle, stake, and rights.
GDS HoldingsFormer parent; reported share repurchase and continuing non-controlling interestPotential related-party and residual ownership exposureReconcile the current cap table, transaction documents, and related-party arrangements.

Reported participation does not establish current ownership percentages, control rights, or cash available to DayOne.

[CO003, CO005, CO006]

1.4 Scale, concentration, and diligence limits

Bloomberg reports US$512 million of revenue for the six months ended June 30, 2026, versus US$151.5 million in the comparable prior-year period. The same article reports an US$81.9 million net loss, while Startup Fortune reports US$77.2 million for that period; the discrepancy should be reconciled to the filed statements rather than averaged. Startup Fortune also reports that one customer represented 69.4% of 2025 revenue and 69.2% in the first half of 2026. This is a single-source concentration disclosure and makes customer identity, contract duration, renewal terms, and related capacity especially important. The available evidence does not establish customer count, a current employee count, total raised across all rounds, or a complete debt and covenant schedule. The Johor land transaction and Finnish development plans show expansion activity, but do not establish powered, permitted, or revenue-generating capacity.[CO010, CO011, CO012, CO013, CO014, CO015]

FO001: Company milestones and reported financing / expansion timeline

Publicly reported corporate, financing, expansion, and IPO events; the June 23 land-sale source does not state a year.

DayOne launch / GDS International origin [CO003]

DayOne rebrand reported [CO003]

Lahti project announced [CO015]

Mezzanine facility reported [CO007]

Initial Series C tranche [CO004]

Nurmijärvi development plan [CO015]

Series C final close [CO004]

Johor land sale to DayOne entity [CO014]

US IPO filing reported [CO008]

IPO delay or smaller offering under consideration [CO009]

[CO003, CO004, CO007, CO008, CO009, CO014, CO015]
Chapter 02

02Market Analysis

2.1 Market boundary and evidence-constrained sizing

The relevant market is leased or contracted data-center capacity, measured by location, power, availability, and rent—not the broader revenue pools for cloud software, AI models, chips, or digital services. This keeps operator capacity distinct from the workloads that create demand. CBRE reported 13.4% year-over-year inventory growth in Q1 2026 across its Singapore, Tokyo, Hong Kong, and Sydney basket, alongside 608.9 MW of regional net absorption; those are growth and quarterly flow measures, not an absolute Asia-Pacific TAM (CM001, CM004, CM015). The region's reported 7% vacancy also masks substantial market variation, from 2% in Singapore to 18% in Hong Kong (CM002). Singapore's average asking rent was $403 per kW/month for 250-to-500-kW capacity, a price proxy for a defined capacity band rather than total market spend (CM003). No retained source supplies a consistent regional inventory denominator, total addressable spend, or a defensible DayOne-specific SAM/SOM. The sizing table and figure therefore preserve distinct measures and leave the monetary market size unquantified (CM015).[CM001, CM002, CM003, CM004, CM015]

Market definition and included spend
Segment or categoryTreatmentBuyer or payer evidenceRelevance and boundary
Hyperscale and wholesale data-center capacity for cloud and AIIncludeHyperscalers and neoclouds are identified as demand cohorts; budget owner is not disclosedDirectly aligns to leased or contracted capacity and power
Retail or enterprise colocation capacityInclude selectivelyCBRE reports asking rent for 250-to-500-kW capacity; named enterprise buyer budgets are not disclosedInclude only where geography and capacity band match the target market
Cloud services and AI application revenueExcludeThe cited sources describe workloads and service demand rather than DayOne selling those servicesCounting service revenue would overstate an infrastructure operator's addressable spend
Power, land, water, and construction inputsExclude from operator revenue; retain as supply constraintsSite developers and utilities are involved; DayOne site-level payer terms are not disclosedThese inputs constrain delivery and capital requirements rather than constitute leased capacity revenue

Analytical boundary uses leased or contracted data-center capacity as the unit; named cohorts are not equivalent to verified budget owners, and no total market spend is inferred.

[CM005, CM006, CM007, CM015]
Market and company sizing lenses
Publisher and dateGeography or populationMetric and valuePeriodMethod or denominatorConfidence and limitation
CBRE Research2026-06-17Asia-Pacific four-market basket; +13.4% inventory growth and 608.9 MW net absorptionQ1 2026Singapore, Tokyo, Hong Kong, and Sydney; growth and quarterly flow rather than absolute stockMedium; does not establish regional TAM
CBRE Research2026-06-17Asia-Pacific vacancy 7%; Singapore 2%; Tokyo 6%; Sydney 4.5%; Hong Kong 18%Q1 2026Regional and named-market vacancy ratesMedium; utilization indicator not revenue or capacity
CBRE Research2026-06-17Singapore average asking rent $403 per kW per monthQ1 2026250-to-500-kW capacity bandMedium; asking-rate sample is not contracted realized revenue
DayOne as reported by The Straits Times and AInvest2026-10-06 and 2026-10-052.3 GW booked; nearly all expected to be delivered by end-2028As of 2026-09-20Company pipelineMedium-high; future delivery is not operational inventory or market size
DayOne as reported by AInvest2026-10-054.6 GW power resources; 2.3 GW booked; 962 MW in serviceAs of 2026-09-20Separate resource, booked, and in-service measuresMedium; do not sum stages or treat resources as contracted capacity
DayOne as reported by ISI Markets2026-08-05More than 1.5 GW of customer bookings since launchThrough August 2026 coverageCumulative bookings since 2022; no definition reconciliation suppliedLow; earlier measure is not directly comparable to later snapshot

CBRE regional measures and company pipeline figures have different populations, periods, units, and denominators. All values are retained as published; none is transformed into a dollar TAM or market share.

[CM001, CM002, CM003, CM004, CM008, CM009, CM013]
FM001: Market boundary and available sizing proxies

The layers narrow from an unquantified market to regional and company capacity indicators; their labels are not proportional market values.

Layer widths indicate hierarchy, not quantitative proportions.

Layers are ordered boundary and capacity indicators, not proportional amounts or nested TAM/SAM/SOM values; no conversion, summation, or share is inferred.

[CM001, CM002, CM003, CM008, CM009, CM015]

2.2 Buyers, demand signals, and adoption path

Public market evidence identifies hyperscalers, neocloud providers, and AI-focused operators as demand cohorts, but does not establish their relative Asia-Pacific spend or the budget holder for an individual deployment (CM005). DayOne's market-facing proposition is long-duration capacity for hyperscale cloud and AI workloads; AInvest describes take-or-pay arrangements, but this is secondary reporting and not a disclosed contract schedule or independently tested retention measure (CM011). DayOne's 2.3 GW of booked capacity as of September 20, 2026, which it expected to deliver nearly entirely by the end of 2028, is evidence of its own contracted pipeline—not the size of the market or realized utilization (CM008, CM009). AInvest separately reports 4.6 GW of power resources and 962 MW in service on that date; these are distinct capacity stages and should not be added together (CM009). Earlier coverage reported more than 1.5 GW of bookings since launch in 2022, without enough method detail to reconcile its cumulative basis precisely to the later snapshot (CM013). The buyer map marks budget ownership and adoption triggers as unverified where the sources do not disclose them.[CM005, CM008, CM009, CM011, CM013]

Buyer and adoption map
Demand cohortBuyer or user evidencePayer and budget ownerWorkflowAdoption trigger and remaining uncertainty
HyperscalersDayOne reporting describes hyperscale technology customers building AI and cloud infrastructureContracting customer is implied; named budget owner and customer identity are not disclosedSecure powered capacity for cloud or AI workloadsNeed for capacity is reported; customer-level contract term and utilization are not public
Neocloud providersCBRE identifies neoclouds as a prominent Asia-Pacific demand source for high-performance computingProvider procurement role is plausible but the budget owner is not specifiedScale compute workloads and capacityMarket demand signal exists; DayOne-specific bookings by cohort are unavailable
AI-focused operators and startupsCBRE cites AI startups among data-center demand sourcesBuyer and payer are not established for DayOneObtain hosting capacity for compute-intensive workloadsDemand depends on power, available sites, financing, and deployment timing
Enterprise and streaming workloadsCNA describes data-center services supporting video streaming and AI; CBRE includes enterprises in broader market demandEnd-user and facility payer may differ; no DayOne-specific enterprise budget evidenceHost digital services and workloadsNo disclosed DayOne mix, enterprise contract count, or budget allocation

Demand cohorts are drawn from reported market categories and company coverage; budget ownership, cohort-level spend, and DayOne customer allocation remain unverified.

[CM005, CM007, CM011, CM012]

2.3 Supply constraints and investment conditions

Demand growth does not translate automatically into deliverable capacity. CBRE attributes longer development timelines in Asia-Pacific core hubs to power availability, higher construction costs, and regulatory complexity, while its Q1 2026 report says availability across major Asia-Pacific markets fell 43% year over year (CM006). Singapore's low vacancy and elevated asking rents are consistent with tight supply, but neither establishes that every project can secure power or achieve the quoted rent. Water is another site-level input: CNA reports that data centers rely heavily on water for server cooling and describes one provider's exploration of analytics-led conservation, which is not a DayOne result or a sector-wide performance benchmark (CM007). Mission Media separately described more than 500 MW of DayOne capacity across Asia-Pacific and Europe, but gave no as-of date or comparable denominator; it should not be reconciled with newer resource, booked, and in-service measures (CM014). Market financing is also exposed to timing risk; Bloomberg reported that DayOne was considering a delay or a smaller US IPO amid data-center market volatility, while The Straits Times described a broader operator IPO pipeline (CM010, CM016). The sector's growth case is therefore conditional on power, permits, water, construction delivery, and financing; project-level costs, customer concentration, and returns cannot be inferred from regional rent or inventory data.[CM002, CM003, CM006, CM007, CM010, CM012, CM014, CM016]

Chapter 03

03Competitors

3.1 Direct hyperscale peers and scale signals

DayOne's company announcement positions it as a multi-market, high-density platform and reports approximately 1 GW of secured customer commitments; those are company claims, not independent operating benchmarks. Data Center Index tracks only two named DayOne campuses and 72 MW across them, explicitly warning that its coverage is not every building. AirTrunk is a direct regional alternative: its reproduced company announcement describes more than 280 MW of planned Johor capacity at JHB3 and JHB4, while saying JHB1 and JHB2 exceed 420 MW and are nearly fully contracted. These figures use different geographies, dates, and pipeline definitions, so they indicate competitive investment rather than a like-for-like capacity ranking.[CP002, CP003, CP004, CP005, CP006]

Competitor profile and evidence-bounded scale
Provider or alternativeCategoryPublic scale or financing signalBuyer focusDifferentiation visible in sourcesLimitation
DayOneDirect hyperscale peerCompany reports approximately 1 GW of secured customer commitments and a Series C above US$2.0 billion; Data Center Index tracks 72 MW across two named campusesHyperscalers and large enterprises, per company descriptionMulti-market platform and high-density AI-ready design, per company announcementTracked campus capacity is explicitly partial; company commitment and financing claims are not audited operating scale
AirTrunkDirect hyperscale peerCompany announcement says JHB3/JHB4 add more than 280 MW and existing JHB1/JHB2 exceed 420 MWGlobal cloud and AI customers, per company announcementJohor hyperscale expansion, recycled-water cooling, and a stated six-market platformCompany-reported planned capacity and customer commitments are not directly comparable with DayOne's tracked campus data
Digital RealtyAdjacent incumbentThree Cyberjaya assets with an approximately 32 MW IT-capacity target, including a future siteEnterprise private AI and multi-cloud users, as reported by Tech Wire AsiaCarrier density, independent fiber paths, and a ServiceFabric connection planned subject to approvalsMalaysia is a smaller disclosed footprint; no comparable pricing or local customer outcomes in assigned evidence
EquinixIncumbent colocation and interconnection providerJohor data-center offering; no Johor capacity figure in the retained pageEnterprise, network, and cloud ecosystem users, per EquinixColocation, Equinix Fabric, Network Edge, and stated global ecosystem scaleUptime and ecosystem metrics are company claims; global totals do not establish Johor-specific performance
Enterprise internal build or private cageSubstitute or status quoNo capacity or cost benchmark in assigned sourcesEnterprises seeking control of private AI environments, as described in a Digital Realty interviewCan keep workloads in an enterprise-controlled environment while connecting to multiple cloudsEvidence is a provider's use-case description, not a customer reference or proof of lower cost

Company announcements and vendor pages are labeled as such; campus, planned, operational, and global platform figures have different scopes. The table is a landscape sample from the assigned pool, not an exhaustive census.

[CP001, CP002, CP004, CP005, CP006, CP009, CP012]

3.2 Incumbents, adjacency, and buyer access

Digital Realty is an adjacent incumbent rather than a direct scale match in the available Malaysia evidence: Tech Wire Asia reports three Cyberjaya assets with an approximately 32 MW IT-capacity target, including a 15 MW AI/HPC facility and a future 14 MW site. Its enterprise pitch is differentiated around private AI environments, multi-cloud access, and interconnection; its ServiceFabric platform is planned for Malaysia in the second half of 2026 subject to licensing approvals. Equinix's Johor page emphasizes colocation, Equinix Fabric, Network Edge, and a broad global network ecosystem, but its customer and network-provider totals are company-reported global figures, not Johor metrics. The map therefore scores evidence visibility, not service quality or actual market share.[CP009, CP010, CP011, CP012]

FP001: Evidence visibility across footprint and customer access

Ordinal map of how much the assigned sources disclose about regional footprint and customer access; it is not a ranking of capability or market share.

X: Publicly described regional footprint evidence (ordinal)
description: 1 = narrow or no footprint detail in this pool; 5 = multiple markets or campuses described.
Y: Publicly described customer access or interconnection evidence (ordinal)
description: 1 = little direct detail in this pool; 5 = explicit customer, network, or multi-cloud access detail.
ItemPublicly described regional footprint evidence (ordinal) (1–5)Publicly described customer access or interconnection evidence (ordinal) (1–5)Context
1. DayOne 5 2 Company announcement names seven markets and about 1 GW of customer commitments; the assigned sources provide limited independent service-level or interconnection detail.
2. AirTrunk 2 3 The assigned sources describe planned and financed Johor campuses; they do not establish an equivalent multi-market footprint comparison.
3. Digital Realty 3 5 Reporting describes a Malaysia campus and an enterprise multi-cloud/interconnection offer; ServiceFabric availability in Malaysia remains subject to approvals.
4. Equinix 2 5 Its Johor page describes colocation and interconnection; displayed customer and network-provider counts are global company claims.
5. Enterprise private AI cage 1 3 A provider-described buyer use case involves an enterprise-controlled private AI environment; no independent customer case is retained.
6. Hyperscaler shared infrastructure 1 1 The interview mentions shared hyperscaler infrastructure as a contrast, but the assigned pool contains no comparative footprint or service detail.

Ordinal scores summarize disclosure in this assigned source set only, not actual capability, quality, or market share. Unknowns are not evidence of absence.

[CP003, CP008, CP010, CP011, CP015]

3.3 Pricing, packaging, and procurement tradeoffs

The retained sources do not establish comparable list prices, realized rates, contract lengths, power commitments, or discounting for DayOne, AirTrunk, Digital Realty, or Equinix. Data-center deals are shaped by capacity, delivery timing, power availability, connectivity, and service scope, but the assigned evidence does not quantify those commercial terms; no price-per-megawatt comparison is defensible here. Digital Realty's reported enterprise-private-AI use case and Equinix's interconnection products show alternatives buyers may evaluate alongside hyperscale capacity, while the evidence does not show which provider wins on total cost. Pricing and contract-level customer evidence should be obtained before asserting a cost moat or undercutting advantage.[CP016]

Pricing and packaging evidence gaps
Provider or alternativePublished price or unit rate in assigned sourcesContract or package detail retainedDiligence implication
DayOneNot established in assigned sourcesNo comparable contract length, power reservation, or realized rate retainedRequest customer-level pricing by market, MW, delivery date, and power terms
AirTrunkNot established in assigned sourcesInvestment and campus announcements do not disclose customer rates or discountsSeparate construction financing from customer economics and realized returns
Digital RealtyNot established in assigned sourcesProduct and connectivity descriptions do not provide a comparable quoteRequest pricing for powered capacity, cross-connects, and managed services
EquinixNot established in assigned sourcesProduct pages identify service categories but no retained Johor rate cardRequest local colocation, port, and interconnection pricing and contract terms

“Not established” means the assigned successful source pool did not provide a comparable term; it does not mean the provider has no public or negotiated pricing.

[CP016]

3.4 Switching costs, moat durability, and displacement risk

The plausible moat is execution at scale: secured customer commitments, nearly contracted campus capacity, and access to power, land, financing, and delivery partners can make a provider difficult to replace once a facility is built and commissioned. The current sources substantiate some announced commitments and investment, but they do not disclose DayOne contract tenor, customer concentration, renewal behavior, switching costs, or site-level delivery performance. Bloomberg's October report that DayOne was weighing an IPO delay or a smaller offering amid data-center volatility, alongside its March report on a potential loan increase, makes financing conditions a material competitive variable rather than proof of distress. Competitor announcements show substantial supply expansion; they do not prove displacement or establish an independent benchmark.[CP002, CP006, CP007, CP013, CP014, CP015]

Durability signals versus unresolved switching evidence
SignalWhat the evidence saysWhat it does not establishUnderwriting implication
DayOne customer commitmentsDayOne's company announcement reports approximately 1 GW of secured commitmentsCustomer identities, concentration, contract tenor, cancellation rights, or realized utilizationObtain anonymized contract schedule and site-level delivery milestones
AirTrunk contracted capacityAirTrunk says JHB1 and JHB2 exceed 420 MW and are nearly fully contractedPricing, duration, renewal, credit quality, or realized marginTreat as a disclosed demand signal, not a verified utilization or margin benchmark
Capital accessBloomberg reported a possible increase to DayOne's existing loan and later reported IPO size/delay optionsCompleted financing terms, available cash, covenants, or a demonstrated funding shortfallStress-test capacity delivery against financing and capital-market access
Incumbent network ecosystemsEquinix lists interconnection products and global customer/network-provider countsJohor-specific switching costs or customer retentionRequest customer references and local network-density data before assigning lock-in
Overall durabilityThe source set shows regional build-out and differentiated interconnection offersNo independent comparative benchmark of DayOne reliability, switching friction, or customer economicsDo not treat pipeline, partnership access, or vendor claims as a proven moat

Signals describe company announcements and reported strategic options, not audited performance. Switching-cost conclusions remain open without customer contracts, retention data, or independent service benchmarks.

[CP002, CP006, CP009, CP012, CP013, CP014, CP015]

3.5 Exhibits

Chapter 04

04Financials

4.1 Monetization and reported traction

Light Reading reports that DayOne defines bookings as IT-power capacity committed by clients under legally binding long-term contracts, and places reported bookings at approximately 2.3 GW across ten Asia-Pacific and European markets. It says seven global hyperscale and technology customers drive most bookings, with about 1.4 GW concentrated in Johor; those are capacity and concentration indicators, not recognized revenue. The same report gives US$512 million of revenue for the six months ending June 30, 2026, without a contract-level bridge from booked capacity to billed or recognized revenue. Startup Fortune reports FY2025 revenue of US$484.3 million versus US$178.1 million in FY2024, but the assigned evidence does not provide revenue mix, realized price per unit, or recognition schedules by service. The tables therefore distinguish reported revenue and contracted capacity from undisclosed monetization details.[CI001, CI002, CI003, CI004, CI008]

Revenue streams and evidence status
Stream or mechanismPublic value or statusQuality interpretationDiligence request
Data-center capacity / hostingApproximately 2.3 GW of bookings; H1 2026 total revenue reported at US$512 millionBookings are contracted IT-power capacity, not recognized revenue; no stream-level reconciliation is disclosedRequest contracted, energized, billed, and recognized capacity by customer and campus
Power, cooling, or other pass-throughsSeparate revenue and pricing treatment not disclosedDo not assume pass-through economics or a margin contributionObtain contract clauses and revenue/cost allocation for power and cooling
Development or other servicesNo separate service revenue is quantified in the retained sourcesMateriality and recurring versus one-time mix are unknownRequest audited revenue by service, geography, and recognition policy

Partial public-source view: Light Reading reports bookings and total H1 revenue, while Startup Fortune reports annual revenue; neither provides a revenue-stream schedule. Bookings are not ARR or recognized revenue.

[CI001, CI002, CI003, CI004, CI008]
Pricing and monetization
Pricing dimensionEvidence statusInterpretationDiligence request
Contract unitLong-term customer contracts commit IT-power capacity; price terms are not reportedCapacity commitment is not a disclosed price or realized revenue rateRequest contract unit, billing trigger, minimum commitment, and escalation terms
List versus realized priceNo list price or realized price per kW/MW is disclosedRevenue cannot be converted into an implied price without delivered capacity and timingObtain price schedules, discounts, incentives, and customer-specific rates
Contract duration and renewalSources describe long-term contracts but do not quantify duration, renewals, or termination rightsRevenue durability and repricing exposure remain unmeasuredRequest contract tenor, renewal, termination, and renewal-price schedule

The table is intentionally partial: Light Reading characterizes bookings as legally binding long-term capacity contracts but supplies no pricing schedule. Null or undisclosed pricing is not zero.

[CI001, CI008]
FI001: Revenue model bridge and missing underwriting links

An illustrative, non-quantified bridge separates reported contracted capacity and top-line revenue from unreported delivery, margin, and cash-conversion inputs.

Node / ConnectionNode / fromToContext
Node 1 Long-term customer capacity booking [contracted-capacity]Light Reading reports legally binding commitments for IT-power capacity.
Node 2 Build, power, and energize campus [campus-delivery]Project-level completion, cost, and energization schedules are not quantified here.
Node 3 Deliver data-center capacity [customer-service]The retained sources do not map individual contracts to delivered capacity.
Node 4 Recognize revenue [recognized-revenue]Light Reading reports US$512 million total revenue for H1 2026; mix and billing bridge are absent.
Node 5 Adjusted EBITDA [adjusted-ebitda]Startup Fortune reports US$205.9 million and a 40.2% margin for H1 2026; adjustments are not reconciled here.
Node 6 Account for operating costs [operating-result]H1 2026 net-loss reports differ: US$81.9 million versus US$77.2 million; gross margin is not reported here.
Node 7 Convert to cash after capex [cash-conversion]Cash flow, working capital, and current liquidity remain unquantified.
Connection 1 Long-term customer capacity booking [contracted-capacity]Build, power, and energize campus [campus-delivery]
Connection 2 Build, power, and energize campus [campus-delivery]Deliver data-center capacity [customer-service]
Connection 3 Deliver data-center capacity [customer-service]Recognize revenue [recognized-revenue]
Connection 4 Recognize revenue [recognized-revenue]Adjusted EBITDA [adjusted-ebitda]
Connection 5 Adjusted EBITDA [adjusted-ebitda]Account for operating costs [operating-result]
Connection 6 Account for operating costs [operating-result]Convert to cash after capex [cash-conversion]

Analytical sequence only, not a disclosed company schedule or a reconciled waterfall; the sources do not connect individual bookings to revenue, margin, or cash.

[CI001, CI004, CI005, CI016]

4.2 Cost structure and unit economics

Light Reading reports a US$81.9 million net loss for the six months ending June 30, 2026, while Startup Fortune reports US$77.2 million for H1 2026; the assigned material does not reconcile the discrepancy (CI005, CI012). Startup Fortune also reports FY2025 adjusted EBITDA of US$180.7 million at a 37.3% margin and H1 2026 adjusted EBITDA of US$205.9 million at a 40.2% margin, alongside FY2025 share-based compensation of US$341.8 million within a US$367.1 million net loss (CI014-CI015). These secondary-source adjusted measures are not audited gross margin, operating cash flow, or cash burn. Channel NewsAsia describes water-intensive cooling across Singapore's data-center sector (CI011), but not DayOne's usage or tariffs. Company power, water, utilization, working-capital, and capex-per-MW inputs remain gaps.[CI004, CI005, CI011, CI012, CI014, CI015]

Unit economics and underwriting inputs
MetricPublic valueConfidence and limitationWhy it matters and diligence request
Revenue, six months ended June 30, 2026US$512 million; Startup Fortune also reports FY2025 revenue of US$484.3 million versus US$178.1 million in FY2024Reported total revenue, not ARR or a stream-level figureReconcile each period to audited statements and segment/customer schedules
Net loss, six months ended June 30, 2026Light Reading: US$81.9 million; Startup Fortune: US$77.2 millionConflicting secondary-source reports; accounting loss is not cash burnReconcile original statement line items, attribution, and period
Largest-customer revenue share69.4% of FY2025 revenue and 69.2% of H1 2026 revenue, as reported by Startup FortuneSingle-customer exposure is material; contract duration and renewal terms are not shownRequest customer-level revenue, backlog, contract terms, and downside sensitivities
FY2025 loss and share-based compensationStartup Fortune reports a US$367.1 million net loss, including US$341.8 million of share-based compensationThe accounting loss and non-cash charge do not establish operating cash flowReconcile net loss to cash flow and adjusted EBITDA
Adjusted EBITDAUS$180.7 million / 37.3% margin in FY2025; US$205.9 million / 40.2% in H1 2026, as reported by Startup FortuneAdjusted EBITDA is not gross margin or independently verified site contributionObtain adjustment definitions, depreciation, power costs, utilization, and site-level margins
Gross margin by campus or serviceNot quantified in the assigned sourcesRequest audited gross margin with power, depreciation, and ramp costs by campus
CAC, sales cycle, or customer paybackNot quantified in the assigned sourcesRequest customer acquisition cost, sales-cycle distribution, and contracted payback
Capex per delivered MW and working capitalNot quantified; industry power and water pressures are not company cost dataObtain project cost-to-complete, working-capital schedule, and capex per energized MW
Cash balance, operating cash flow, and runwayNot established by the retained reportingRequest latest audited cash, quarterly burn, committed capex, debt maturities, and runway

Revenue, loss, concentration, and adjusted EBITDA values are attributed to the named reports and preserve their periods. Nulls mean the assigned evidence does not quantify the metric, not that the value is zero; the H1 2026 loss discrepancy is unresolved.

[CI004, CI005, CI011, CI012, CI013, CI014, CI015]

4.3 Capital adequacy and financing dependency

DayOne's June 5, 2026 release announced US$4.5 billion of gross Series C proceeds and said it could consider additional equity or debt depending on funding needs and market conditions (CI006-CI007). An October 2025 ICEF roadmap reported US$3.58 billion (SG$4.6 billion) in green financing for Malaysian development (CI016). ISI Markets later reported that the company was said to be negotiating an expansion of a corporate loan facility to as much as US$7 billion, not that a facility had closed or been drawn (CI010). Bloomberg reported that a delay or a smaller US$2.5-3 billion IPO was under consideration, with no final decision (CI009). These gross, historical, or conditional financing figures do not establish current liquidity; cash, burn, committed capex, debt terms, and runway remain unavailable in the assigned sources.[CI006, CI007, CI009, CI010, CI016]

4.4 Underwriting verdict

Reported revenue growth and contracted capacity demonstrate scale, but they do not establish revenue quality, durable margins, or capital adequacy. Startup Fortune reports that one customer represented 69.4% of FY2025 revenue and 69.2% in H1 2026 (CI013); customer-level pricing, renewal sensitivity, and sales efficiency remain unquantified. The conflicting H1 loss figures require reconciliation to the primary statements before relying on adjusted margins. Do not infer ARR from bookings, cash burn from accounting loss, or cash available from gross financing proceeds. Underwriting needs executed customer contracts and a billing bridge, site-level delivered capacity and costs, audited cash-flow and margin reconciliations, and a current debt and capex schedule. Until then, the financial picture is promising on scale but incomplete on economics and funding runway.[CI005, CI008, CI009, CI013, CI014, CI015, CI016]

4.5 Exhibits

Chapter 05

05Product & Technology

5.1 Product and customer workflow

DayOne describes itself as a Singapore-headquartered platform that develops and operates next-generation data centers for hyperscalers and enterprises; a provider directory also describes cloud, AI, and high-performance workloads. In practical terms, the offered product is campus capacity and associated colocation infrastructure, not a disclosed standalone software product. DayOne's June 2026 release says it had secured more than 1.5 GW of total bookings since inception, but bookings are not commissioned capacity, utilization, or independently verified customer deployments. The company also calls its delivery model proprietary without publishing the technical or operating procedures that would establish how it differs from other operators. The module and workflow tables keep those claims separate from demonstrated customer outcomes.[CE001, CE003, CE016]

Product module and asset matrix
Module or assetCustomer or userPublicly stated statusClaimed differentiationDiligence gap
Hyperscale campusesHyperscalers and large enterprisesCompany says campuses operate or are under development across eight marketsHigh-capacity AI-ready infrastructure and regional reachCurrent commissioned capacity and site-by-site operating status are not reconciled in the assigned sources.
SG1 Singapore facilityGPU and cloud workload customers20 MW facility; Phase One targeted for ready-for-service in 2026 in the July 2025 announcementHigh-density GPU support and hybrid air/liquid coolingConfirm current RFS status, energized IT load, rack density, and customer acceptance.
Energy sourcing and SOFC pilotSingapore facility users and utility partnersTen-year PPA described; on-site SOFC is a proof of conceptRenewable-energy certificates and testing of hydrogen-based energyObtain metered energy mix, carbon accounting, fuel-cell operating data, and fallback design.
Tropical cooling R&DData-center operators and customersNUS research partnership announced for pilot-scale testingTesting novel cooling approaches in tropical conditionsRequest test results, boundary conditions, and evidence of production deployment.

Statuses are attributed to the cited company announcement or provider listing; planned schedules, bookings, and proof-of-concept work are not treated as commissioned capacity or measured performance.

[CE001, CE002, CE003, CE004, CE005, CE006, CE007, CE008]
Workflow and use-case table
User jobCurrent workflow or needDayOne solution describedMeasurable benefit statedLimitation
Hyperscaler capacity deploymentSecure large-scale data-center capacity across marketsDevelop and operate hyperscale campuses and offer colocation infrastructureCompany reports more than 1.5 GW of total bookings since inceptionBookings are not live capacity, utilization, deployment speed, or customer outcomes.
AI and GPU computeHost high-density compute workloadsSG1 announcement describes high-density GPU support and hybrid air/liquid coolingNo measured rack density, PUE, or cooling result is providedDesign description is not an operating benchmark.
Lower-carbon facility powerSupply electricity while managing energy and sustainability constraintsSG1 PPA with bundled RECs and an SOFC proof of conceptNo measured renewable share, emissions intensity, or fuel-cell output is disclosedPPA and pilot descriptions do not establish realized site-wide performance.

Benefits are limited to the source's stated capacity-booking metric or to the absence of measured outcome data in the reviewed materials; no conversion from bookings to operating capacity is implied.

[CE003, CE005, CE006, CE007, CE015]

5.2 Campus footprint and maturity

Public descriptions span Singapore, Malaysia, Indonesia, Thailand, Japan, Hong Kong, Finland, and Spain, but the sources mix operating, under-development, and planned assets. The clearest facility-level description is the July 2025 announcement for SG1: a 20 MW Singapore facility with about 40,000 square meters of gross floor area and Phase One targeted to be ready for service in 2026. That is a dated forward schedule, not evidence that the phase is now commissioned. Directory and media capacity figures use different labels and do not provide a reconciled, current site-by-site status. Product diligence should therefore distinguish booked demand and campus count from live IT load, energized capacity, and customer-accepted deployments.[CE002, CE003, CE004, CE010, CE011]

5.3 Architecture and deployment model

The Singapore announcement describes high-density GPU support with hybrid air and liquid cooling, a ten-year power purchase agreement backed by bundled renewable energy certificates, and a solid-oxide fuel-cell proof of concept. It also describes a research partnership with the National University of Singapore to test cooling solutions in a tropical environment. These are concrete design and development signals, but the sources provide no measured PUE, rack density, cooling performance, energy mix, or reliability results. The architecture figure groups only the customer interface, campus design, and energy/research features explicitly described in the pool; it is not a verified engineering schematic.[CE005, CE006, CE007, CE008, CE015]

Technology and operating architecture
Layer or processRole in the offerDependency or statusPrincipal technical risk or diligence question
Regional campus developmentProvides capacity in APAC and European marketsCompany reports operation or development across eight marketsWhat capacity is energized, under construction, permitted, or only planned at each site?
GPU and cooling designSupports high-density AI workloadsSG1 is described with GPU support and hybrid air/liquid coolingWhat are rack-density limits, PUE, cooling-water use, and measured thermal performance?
Power sourcingSupplies facility electricitySG1 PPA backed by bundled RECs; SOFC is a proof of conceptWhat are actual energy sources, reliability arrangements, and pilot results?
Delivery modelCoordinates development and operationsCompany calls its integrated delivery model proprietary; detail is not publishedWhich components are standardized, prefabricated, or controlled in-house, and what delivery evidence exists?
Research and assuranceTests cooling and supports facility qualityNUS pilot-scale research announced; SG1 certifications were described as applications to be madeRequest published test results, completed site certifications, and independent security/reliability attestations.
Capacity reportingIndicates scale of the deployment pipelineCompany reports over 1.5 GW in total bookings; third-party articles use distinct operating, under-construction, and reserved capacity labelsReconcile dates, denominators, and commissioning status before treating reported capacity as delivered product.
Capital timingSupports financing of campus developmentBloomberg reports possible IPO delay or size reduction; Startup Fortune frames the listing as a test of investor appetiteAssess whether financing changes affect site schedules; neither report identifies a technical failure.
Performance evidenceValidates the delivered serviceThe assigned source texts provide no measured uptime, PUE, rack density, cooling performance, or customer-accepted operating resultsRequest current site metrics and independent assurance.

This is a source-bounded operating map, not an engineering design. Planned facilities, research, capacity reports, and certification applications remain distinct from commissioned systems and completed assurance. Third-party capacity labels are not reconciled because their dates and definitions differ.

[CE002, CE003, CE004, CE005, CE006, CE007, CE008, CE009, CE011, CE014, CE015, CE016]
FE001: Publicly described product and operating layers

Source-bounded view of customer workloads, disclosed campus design, and announced energy and research interfaces; it does not represent a verified engineering architecture.

Customer groups
Modules
  • Hyperscalers
  • Cloud platforms
  • Large enterprises
Workloads
Modules
  • AI and GPU compute
  • Cloud workloads
Facility offer
Modules
  • Hyperscale campuses
  • Wholesale colocation
Compute and cooling
Modules
  • High-density GPU support
  • Hybrid air and liquid cooling
Development model
Modules
  • Modular or prefabricated development models
  • Integrated delivery model, details undisclosed
Power and research
Modules
  • Ten-year PPA with bundled renewable energy certificates at SG1
  • SOFC hydrogen-based power proof of concept
  • NUS pilot-scale cooling research partnership
  • Renewable and low-carbon pathways claimed for the portfolio
[CE001, CE005, CE006, CE007, CE008, CE016]

5.4 Differentiation, trust, and diligence limits

DayOne's materials emphasize rapid deployment, high-density designs, low-carbon power pathways, and an integrated delivery model. The assigned sources do not establish comparative performance or disclose the methods behind these claims. The Singapore announcement says LEED Platinum and BCA Green Mark Platinum certifications would be applied for; a directory separately lists LEED statuses for several Johor buildings. Neither statement establishes certification of SG1. A peer operator's site descriptions are useful only as competitor-issued context, not independent benchmarks. Bloomberg's report of possible IPO delay or size reduction, alongside Startup Fortune's framing of the offering as a test of investor appetite for AI infrastructure, adds capital-timing uncertainty, not evidence of a technical failure. Current site-level security, redundancy, incident, and service-level evidence remains a material diligence request.[CE009, CE012, CE013, CE014, CE015, CE016]

Chapter 06

06Customers

6.1 Buyer segments and the regional proposition

Public descriptions place DayOne between infrastructure development and customer operations: it secures and operates powered, cooled facilities, while customers install their own computing and network equipment. Indexed.vc characterizes its target market as hyperscalers, cloud providers, and enterprises; AI in Asia also describes cloud and AI operators as users. These are reported target segments, not a verified account roster. YesPress presents Singapore, Johor, and Batam as a connected SIJORI proposition, but does not identify which customers use each location or disclose customer outcomes there.[CU001, CU002, CU012]

Customer segments and evidence status
Segment / relationshipBuyer, user, or payerUse case / scaleEvidence statusDiligence limitation
Hyperscalers and cloud providersLarge-capacity buyer; customer installs compute and network equipmentPowered, cooled colocation and interconnectionReported target segment; no named DayOne account roster in the assigned sourcesContracted capacity, customer count, and site-level use are not disclosed here
AI operatorsOperator of customer-owned computeRegional capacity for cloud and AI workloadsDescribed as a user segment by AI in Asia and YesPressNo named tenant, production status, or customer-quoted outcome is verified
Enterprise customersEnterprise buyer or workload ownerColocation and interconnection servicesIndexed.vc lists enterprises among target customer typesNo named DayOne enterprise deployment is established by that profile
Public-cloud alternatives, not verified DayOne customersCloud buyers choosing public cloud or colocationLocal cloud-region access in Malaysia and the SIJORI clusterMicrosoft and Oracle publish regional service informationThese sources do not establish DayOne customer overlap or substitution rates

Segment labels combine third-party company profiles and official competitor disclosures; target segments and adjacent alternatives are not proof of active DayOne customers.

[CU001, CU002, CU009, CU010, CU011]

6.2 Bookings are not yet a retention or utilization record

Two publications report more than 1.5 GW of customer bookings since DayOne's 2022 inception, with YesPress attributing the figure to a June 2026 company statement. Separately, YesPress reports 1,250 MW of committed and 444 MW of billable IT power at December 31, 2025. Those are different measures and reporting dates; the available evidence does not reconcile them into a common cohort or show how much booked demand became energized, occupied, and invoiced. The gap is commercially important for a capital-intensive operator, but it is not a calculated conversion rate.[CU003, CU004, CU005]

Customer adoption and operating-capacity indicators
MetricValue and periodSource attributionConfidence / interpretationMissing denominator or caveat
Customer bookingsMore than 1.5 GW since 2022; reported by June 2026YesPress and ISI Markets report the figureMedium; secondary reporting of a company statementBookings are not identified as active, billable, or utilized capacity
Committed IT power1,250 MW at December 31, 2025YesPressLow; one secondary sourceDefinition and relationship to customer bookings are not reconciled
Billable IT power444 MW at December 31, 2025YesPressLow; one secondary sourceNot customer count, utilization, or revenue per MW
Retention and renewal metricsNot reported in the reviewed assigned sourcesEvidence gap; not a zero valueUnresolvedNRR, GRR, churn, renewals, cohorts, and contract duration are unavailable

The reported booking, committed, and billable measures have different labels and vintages. No booking-to-billable conversion, utilization rate, or retention metric is calculated from them.

[CU003, CU004, CU005]
FU001: From capacity request to billable use

Conceptual customer path from capacity need to billing; the evidence does not establish cohort conversion, retention, or a measured expansion loop.

[CU001, CU003, CU004, CU005, CU008, CU012]

6.3 Concentration is visible; named deployment proof is not

Startup Fortune reports that the largest customer represented 69.4% of 2025 revenue and 69.2% of first-half 2026 revenue. Mukhbir, summarizing Reuters Breakingviews, attributes 84.3% of first-half 2026 revenue to ByteDance and Oracle together. The attribution is secondary reporting rather than a company-named customer reference: Startup Fortune says the preliminary prospectus did not name the largest customer. The assigned sources do not provide named site-level deployment status, contract duration, customer-quoted outcomes, or an independently validated reference.[CU006, CU007, CU008]

Named customer proof table
Customer or proof categoryReported segment / metricProduction status and outcomeSource attributionLimitation
Largest customer, not named in the prospectus according to Startup Fortune69.4% of 2025 revenue; 69.2% of first-half 2026 revenueNo deployment site, contract term, or customer-quoted outcome reportedStartup Fortune; Mukhbir separately reports roughly 69% for ByteDance via ReutersRevenue share, not MW share or customer count; identity is not company-confirmed
ByteDance and Oracle, identified only in secondary reportingReported together at 84.3% of first-half 2026 revenueIndividual customer shares and named site deployments are not providedMukhbir's summary of Reuters Breakingviews; Startup Fortune describes the prospectus as not naming the largest customerNot a company-issued customer reference; no individual Oracle share is stated
Named deployment, pilot, or customer outcomeNo named DayOne customer deployment or outcome is documented in the reviewed textsProduction versus pilot status and reference quality are unverifiedYesPress describes customer names as mostly confidential; AI in Asia gives customer categories, not named referencesAbsence in this assigned evidence set is not proof that no such deployments exist

This is a partial sample of publicly reported customer proof. The named-account attribution is secondary, while site-level deployment and outcome evidence remains unavailable.

[CU006, CU007, CU008]

6.4 Retention and workload alternatives remain diligence priorities

None of the reviewed customer-focused sources supplies NRR, GRR, churn, renewal, cohort, or contract-duration metrics, so booking scale and revenue concentration cannot establish customer durability. Public cloud alternatives also matter to buyer choice: Oracle lists live regions in Batam, Kulai, and Singapore, while Microsoft's November 2025 announcement described a planned Johor Bahru region and named Malaysian Azure users. These are market alternatives and Microsoft customer examples, not evidence that those organizations are DayOne customers or that the services are interchangeable for every workload.[CU009, CU010, CU011]

Chapter 07

07Risks

7.1 Capital-market timing and funding dependence

The financing thesis is exposed to public-market timing as well as construction capital needs. Bloomberg reported on October 21, 2026 that DayOne was weighing a delay or smaller US IPO and that a smaller offering could raise US$2.5–3.0 billion, roughly half the original target (CR001, CR002). Earlier coverage by Mission Media described an approximately US$5 billion target, so the newer report is evidence of a changed range under volatile market conditions, not proof that an offering was cancelled or repriced (CR002). DayOne announced definitive agreements for more than US$2.0 billion of Series C equity in January 2026; its release said this followed US$1.9 billion of Series A and B equity; the company separately described an up-to-€1 billion mezzanine facility secured in 2025 (CR003, CR004, CR016). ISI Markets later reported that an expansion of a corporate loan facility to as much as US$7 billion was being negotiated, not closed (CR015). These amounts describe financing raised, announced, or under discussion; they do not establish current unrestricted cash, drawn debt, covenants, or funding available for specific projects.[CR001, CR002, CR003, CR004, CR015, CR016]

7.2 Customer concentration and contract visibility

The assigned evidence does not quantify customer concentration. DayOne's January 2026 release said its expansion investments would support approximately 1GW of secured customer commitments (CR005), while ISI Markets later reported more than 1.5GW of customer bookings since the company launched in 2022 (CR006). Those differently named totals do not disclose a common measurement date, definition, customer split, or contract status, so they should not be added or treated as a reconciled contracted-MW backlog. Neither source provides customer-by-customer revenue, contracted MW, renewal protection, or cancellation rights. A large counterparty deferral could still reduce utilization and cash recovery, but its magnitude cannot be established from aggregate bookings. Diligence should reconcile booking-to-contract conversion and customer exposures against the campus capex schedule before relying on demand visibility.[CR005, CR006]

Partner, customer, and financing dependency register
DependencyReported exposureFailure scenarioMitigation visibilityResidual diligence
Customer bookings and contract conversionDayOne reported approximately 1GW of secured customer commitments; ISI Markets separately reported more than 1.5GW of bookings since launch in 2022.A large-customer deferral or failed booking-to-contract conversion could reduce utilization and cash recovery.Aggregate demand is reported, but customer-level exposure and contract protections are not disclosed.Reconcile metric definitions, customer concentration, contract tenor, take-or-pay terms, renewal rights, and customer credit.
IPO market and project financingBloomberg reports a possible delay or US$2.5–3.0B smaller IPO; ISI Markets says a corporate loan expansion to as much as US$7B was being negotiated.Reduced or delayed proceeds could require reprioritization, additional debt, or slower campus delivery.Company-announced Series C equity and earlier mezzanine financing are visible, but funding availability and debt terms are not.Confirm offering status, unrestricted cash, debt drawn, maturities, covenants, collateral, and committed project funding.
Power supplier and energy attributesData Center Dynamics reports a 10-year PPA with Sembcorp and bundled renewable-energy certificates.A delivery, pricing, or grid-connection mismatch could constrain power-intensive capacity.A long-duration agreement is reported; volumes, site allocation, and firm delivery protections are not.Review contract schedule, curtailment terms, price escalators, REC accounting, and backup arrangements.
Local regulators, utilities, and technical partnersReported dependencies include Singapore's capacity pilot, Thailand's BOI framework, and an NUS cooling research partnership.Approval, utility, or validation delays may defer site milestones or prevent incentive eligibility.Public sources identify the frameworks and partners but not site-specific approval completion.Obtain a project-by-project responsibility matrix, approval tracker, and partner service-level commitments.

Aggregate customer-demand and financing figures retain their stated labels, periods, and uncertainty. The cited evidence does not disclose customer shares, contract terms, current cash availability, or project-specific partner obligations.

[CR001, CR003, CR004, CR005, CR006, CR009, CR011, CR015, CR016]

7.3 Permitting, power, and resource constraints

DayOne's Singapore buildout sits within a deliberately limited capacity-allocation regime. Data Center Dynamics reported that SG1 is a 20MW project with Phase I scheduled for ready-for-service in 2026, and that DayOne received capacity through a pilot scheme in which four operators shared 80MW (CR007, CR008). Reed Smith describes Singapore's measured growth, land, power, and water constraints, noting that no new capacity had been allocated since the 2023 pilot and that new projects face stringent approval and efficiency standards (CR011). This establishes regulatory and resource exposure, not a finding that DayOne lacks a permit or allocation. For Thailand, a July 2026 legal update describes a PUE threshold of 1.3 for high-efficiency data centers seeking tax privileges, alongside security, redundancy, water-management, and workforce conditions (CR012). It also reports government attention to energy, water, and community impacts (CR013). The assigned sources do not establish which DayOne sites have completed each local approval.[CR007, CR008, CR011, CR012, CR013]

Regulatory / legal risk register
Risk and evidenceLikelihoodImpactMitigation visibilityResidual exposure and diligence trigger
Singapore capacity and approval: SG1 was reported within the 80MW pilot allocation shared among four operators.Medium; future capacity is constrained, but the cited report says DayOne received pilot capacity.High; power, land, and approval constraints can affect expansion timing.Partial; a pilot allocation is reported, but site-level approvals and available capacity are not established.Confirm permits, allocated MW, grid connection, and remaining phase milestones for each Singapore site.
Thailand BOI eligibility: DCD reports a DayOne site groundbreaking; the 2026 BOI framework sets conditions for high-efficiency data centers seeking tax privileges.Medium; the framework is reported, but the site's application and compliance status are not.High; failure to satisfy applicable conditions could affect incentives, approvals, or schedule.Unverified for DayOne; the source gives general requirements and no DayOne site assessment.Obtain site-specific BOI status, PUE design basis, water plan, security controls, and workforce commitments.
Power and water availability: Singapore and Thailand sources describe constrained power, water, and community considerations.Medium; the exposure is market-level and site-specific availability is not reported.High; an unavailable resource or delayed connection can constrain commissioning and utilization.Partial; DayOne's reported Sembcorp PPA and renewable certificates are mitigants, but volumes and firmness are undisclosed.Verify contracted MW, connection dates, water balances, and contingency supply for each campus.
Cross-market approvals: each new site must meet local energy, land-use, and technical requirements.Medium; DayOne has a multi-country development plan, while site-level completion evidence is limited.High; regulatory slippage can defer revenue and increase carrying costs.Partial; company-reported local partnerships do not substitute for permit and milestone evidence.Reconcile a country-by-country permit register with construction and ready-for-service schedules.

Partial, evidence-based register for the Singapore and Thailand requirements visible in assigned sources; it is not an exhaustive list of DayOne permits or jurisdictions. Likelihood and impact are analyst triage categories, not measured probabilities.

[CR007, CR008, CR009, CR011, CR012, CR013]

7.4 Commissioning, reliability, and operational execution

A schedule milestone is not operating proof: the SG1 Phase I date is described as scheduled for 2026, while the assigned sources do not confirm commissioning, utilization, uptime, or achieved energy performance (CR007). Data Center Dynamics reports a 10-year power purchase agreement with Sembcorp backed by bundled renewable-energy certificates (CR009). The agreement is a visible mitigation, but it does not establish delivered power volumes, firm grid capacity, or production- scale cooling results. A DayOne mechanical-engineer listing hosted by Simplify describes preventive and corrective maintenance, vendor coordination, safety audits, and 24/7 operations at Lahti (CR014). This is company-issued evidence of stated responsibilities, not evidence of a staffing shortage or an incident. Portfolio growth across countries increases the importance of site-by-site commissioning, maintenance, and regulatory controls; the evidence does not permit a claim that any outage or safety event has occurred.[CR007, CR009, CR014]

Operational, quality, and reliability risk register
Failure modeLikelihoodSeverityMitigation maturityUnresolved evidence and monitoring indicator
SG1 Phase I commissioning or schedule slippageMedium; Phase I was scheduled for 2026, with no completion confirmation in assigned sources.High; delayed ready-for-service capacity can defer utilization and customer delivery.Partial; a project schedule and reported pilot allocation are visible.Track delivered phase MW, customer acceptance, commissioning tests, and any schedule revision.
Cooling-system performance under high-density or tropical loadsMedium; the company describes cooling initiatives, while production-scale performance is not reported.High; insufficient cooling can constrain safe, reliable IT load.Early-stage evidence; NUS testbed collaboration is reported as research and development.Request site PUE, thermal redundancy, liquid-cooling acceptance, and measured seasonal performance.
Power procurement or grid connection does not match project rampMedium; a 10-year PPA is reported, but volume, delivery profile, and grid conditions are not disclosed.High; power shortfall may delay commissioning or limit sellable capacity.Partial; Sembcorp agreement and renewable certificates are reported, without site-level delivery evidence.Reconcile contracted load, grid milestones, backup capacity, and customer ramp dates.

Risk ratings are qualitative analyst assessments. The cited partnership reports describe planned controls, not independently verified uptime, safety, or operating results; no incident absence is inferred.

[CR007, CR009, CR010]

7.5 Residual exposure and decision triggers

The risk ranking below is qualitative and reflects the magnitude of disclosed exposure and the visibility of mitigation in the assigned evidence, not a measured probability model. Bloomberg's report of possible IPO delay or downsizing is the clearest current market signal; site delivery and regulatory risks remain contingent on approvals, power, and commissioning evidence. Aggregate customer commitments and bookings do not establish concentration or contract durability. The company describes equity funding and customer commitments, and Data Center Dynamics reports renewable-power procurement, but sources do not disclose current cash availability, debt covenants, site-specific approvals, or independently verified operating KPIs (CR001, CR003, CR005, CR006, CR009, CR015, CR016). Re- underwrite if a material IPO delay or smaller proceeds leaves committed projects without identified financing; if customer-level exposure or protections prove concentrated; or if a campus misses a disclosed ready-for-service milestone without replacement power or financing. These are diligence and thesis-break tests, not predictions of failure.[CR001, CR003, CR005, CR006, CR007, CR009, CR015, CR016]

FR001: Evidence-weighted residual risk map

Qualitative exposure and mitigation visibility based on assigned sources, not a probability model.

[CR001, CR005, CR006, CR007, CR009, CR010, CR011, CR012, CR014]

7.6 Exhibits

Chapter 08

08Valuation

8.1 Investment thesis and anti-thesis

DayOne's investment case rests on reported demand and access to capital: coverage describes a US$4.5 billion Series C, more than 1.5 GW of capacity bookings, and first-half 2026 revenue growth. Those are meaningful scale signals, but reported bookings are not recognized revenue and revenue is not cash generation. The same reporting gives a first-half net loss and warns of dependence on a limited number of hyperscale customers. On the supply side, CBRE and the IEA identify power availability, grid connections, and approvals as constraints on where and how quickly data-center capacity can be delivered. The thesis therefore depends on converting demand into energized, profitable capacity without losing access to customers or financing. (CV001, CV006-CV012)[CV001, CV006, CV007, CV008, CV009, CV010, CV011, CV012]

Thesis and anti-thesis
ArgumentSupporting evidenceCounterevidence or uncertaintyWhat would change the view
Demand and scaleReports cite more than 1.5 GW of capacity bookings and first-half revenue growth.Bookings are not revenue; reported first-half net loss widened.Audited occupancy, contracted-versus-delivered MW, and cash conversion.
AI infrastructure opportunityCBRE and the IEA describe rising data-center demand and investment.Power availability, grid connections, and approvals constrain delivery.Site-level energized MW, power contracts, and schedule performance.
Capital accessCoverage reports a US$4.5 billion Series C and IPO preparation.The proposed expanded loan facility is not shown as closed, and final IPO terms remain unsettled.Audited debt, covenant, preference, and project-finance disclosures.
Public-market exitAn October report described an IPO filing and an earlier report named proposed underwriters.Bloomberg later reported possible delay or smaller proceeds; customer and ownership risks remain.Final registration statement, offer price, allocation, and governance terms.

Company-specific operating and transaction metrics are reported figures, not independently audited in this evidence set; diligence items are decision tests rather than claims that the missing information is unavailable elsewhere.

[CV001, CV003, CV004, CV005, CV006, CV007, CV008, CV009, CV010, CV011, CV012, CV014, CV015]
FV001: Evidence-to-recommendation logic

Reported demand and scale are offset by delivery, profitability, and IPO-pricing uncertainty.

Node / ConnectionNode / fromToContext
Node 1 AI and data-center demand [demand]
Node 2 Reported DayOne capacity bookings [bookings]
Node 3 Revenue growth alongside net losses [economics]
Node 4 Power and grid constraints [delivery]
Node 5 IPO size and valuation unsettled [pricing]
Node 6 Research-more pending audited terms [decision]
[CV004, CV005, CV006, CV007, CV010, CV011, CV012, CV016]

8.2 Price discipline and public-market evidence

The approximately US$20 billion figure in the assigned reporting is a reported target or market estimate, not an official company or investor valuation. The reported US IPO proceeds target also needs to be kept separate from enterprise value, equity value, and investor return: Bloomberg later reported that DayOne was weighing a delay or an offering raising US$2.5 billion to US$3 billion. Neither report supplies an offer price, share count, or a complete capital structure. GDS Holdings' market capitalization is a contextual public-market observation, not a like-for-like DayOne valuation multiple; the companies' business perimeters and ownership differ. With no audited standalone earnings, net debt bridge, or final terms in this evidence set, an entry price or target return would be false precision. (CV002-CV005, CV013-CV016)[CV002, CV003, CV004, CV005, CV013, CV014, CV015, CV016]

Recommendation summary
DimensionAssessmentDecision implication
Recommendationresearch-moreDo not underwrite a buy at the reported target without verified offering terms.
ConfidencemediumThe available company-specific evidence is largely secondary reporting.
Risk ratinghighReported customer concentration, operating losses, power constraints, and financing uncertainty remain material.
Valuation stanceunknownThe reported US$20 billion figure is not an official mark tied to audited earnings or cash flow.
Entry disciplineRequire offer price, share count, net-debt bridge, and customer and contract disclosuresDo not set a target return or exit multiple until those inputs are available.

IPO terms and operating figures are attributed to the cited reports; the ratings and decision implication are this chapter's evidence-limited assessment, not a disclosed company or investor judgment.

[CV002, CV003, CV004, CV005, CV006, CV007, CV008, CV009, CV011, CV016]

8.3 Scenario framing and exit readiness

The scenarios below are conditional decision cases, not forecasts or probability-weighted price targets. The bull case requires disclosed financials, reliable power delivery, customer durability, and a receptive IPO window; its only available valuation reference is the reported approximately US$20 billion target. The base case allows for a resized or delayed transaction while capacity and financing execution remain central. The bear case is a delay or repricing if market access, customer concentration, losses, or power constraints worsen. Bloomberg's reported US$2.5 billion–US$3 billion alternative refers to potential IPO proceeds, not company valuation. No numerical return, probability, or downside range is supportable until primary offering terms and audited standalone financials are available. (CV004-CV009, CV011, CV012, CV015, CV016)[CV004, CV005, CV006, CV007, CV008, CV009, CV011, CV012, CV015, CV016]

Conditional bull, base, and bear cases
Case and assumptionsValuation anchor or rangeReturn logicProbability signalDownside trigger
Bull: audited growth converts into durable cash flows; power delivery and customer retention remain strong; the IPO window reopensNo supported range; approximately US$20 billion is a reported target, not an appraisal.No per-share return can be calculated without an offer price and share count.Unassigned; no evidence supports a numeric probability.Customer loss, power delays, or failure to convert bookings into profitable capacity.
Base: expansion continues but power access and capital availability govern timing; an IPO may be resized or delayedNot estimable from assigned public evidence.Potential US$2.5 billion–US$3 billion IPO proceeds are not a valuation or return measure.Unassigned; no evidence supports a numeric probability.Prolonged delay, higher financing costs, or persistent operating losses.
Bear: market access deteriorates or delivery, customer, or financing risks worsenNo supportable numerical downside range; the reported US$20 billion figure is not a floor.A downside return requires a market price, share count, and capital-structure bridge.Unassigned; no evidence supports a numeric probability.IPO cancellation or repricing, customer concentration, or power and approval bottlenecks.

These are conditional scenarios, not forecasts. No numerical probability, target return, or valuation range is supplied because the assigned sources do not provide enough primary financial or offering data. IPO proceeds are kept distinct from company valuation.

[CV002, CV004, CV005, CV006, CV007, CV008, CV009, CV011, CV012, CV016]

Disclaimer

This report is a public-evidence diligence snapshot, not investment advice. Important financial, legal, technical, and contractual facts remain non-public and should be verified directly with management and primary documents before any investment decision.

Evidence index

Claims
IDStatementConfidenceSources
CO001 DayOne describes itself as a Singapore-headquartered developer and operator of hyperscale data centers serving hyperscalers and large enterprises. High SO006, SO009
CO002 DayOne presents its SIJORI model as an interconnected platform spanning Singapore, Johor, and Batam. Medium SO009
CO003 Reporting describes DayOne as succeeding GDS International and originating from GDS Holdings, with accounts placing launch or separation around 2022 and rebranding in 2025. Medium SO002, SO004, SO005
CO004 ISI Markets and Data Center Dynamics report that DayOne closed a US$4.5 billion gross-proceeds Series C in June 2026 after an initial US$2 billion tranche in January. Medium SO005, SO008
CO005 Coatue and Hillhouse led the Series C, while the Indonesia Investment Authority and Achi Capital Partners participated as new investors, according to the financing reports. Medium SO005, SO008
CO006 Startup Fortune reports that GDS Holdings sold US$385 million of DayOne shares back to the company in January 2026, while Mission Media reports that GDS retained a non-controlling stake. Medium SO002, SO004
CO007 Data Center Knowledge reports a December 2025 mezzanine financing facility of up to US$1.2 billion from Brookfield and a global sovereign investor. Medium SO010
CO008 Bloomberg reported a US IPO filing on October 5, 2026, while other coverage described a roughly US$5 billion proceeds target and a possible US$20 billion valuation. Medium SO001, SO002, SO004
CO009 Bloomberg reported on October 21, 2026 that DayOne was weighing an IPO delay or a reduced offering of US$2.5 billion to US$3 billion, citing people familiar with the matter. Medium SO003
CO010 Bloomberg and Startup Fortune report US$512 million of revenue for the six months ended June 30, 2026, versus US$151.5 million in the comparable prior-year period. High SO001, SO002
CO011 Bloomberg reports a net loss of US$81.9 million for the six months ended June 30, 2026. Medium SO001
CO012 Startup Fortune reports a net loss of US$77.2 million for the six months ended June 30, 2026, conflicting with Bloomberg's US$81.9 million figure. Low SO002
CO013 Startup Fortune reports that DayOne's largest customer accounted for 69.4% of 2025 revenue and 69.2% of revenue in the first half of 2026. Low SO002
CO014 The Edge Malaysia reports that Paragon Globe agreed to sell 26.42 hectares of freehold Iskandar Puteri land to DayOne Data Centers Malaysia III Sdn Bhd for RM398.11 million cash; the fetched text does not state the year. Medium SO007
CO015 Data Center Knowledge reports DayOne's Finland expansion plans, including a Nurmijärvi project with up to 560 MW of grid-power potential subject to approvals and permits. Medium SO010
CO016 The assigned company-facing pages describe an experienced leadership team but do not name founders, executives, or directors in the reviewed text. Medium SO006, SO009
CM001 CBRE reported Asia-Pacific data-center inventory growth of 13.4% year over year in Q1 2026 across Singapore, Tokyo, Hong Kong, and Sydney. Medium SM001
CM002 CBRE reported Q1 2026 vacancy of 7% across Asia-Pacific, with Singapore at 2%, Tokyo at 6%, Sydney at 4.5%, and Hong Kong at 18%. Medium SM001
CM003 CBRE reported Singapore's average asking rent at $403 per kW per month in Q1 2026 for 250-to-500-kW capacity. Medium SM001
CM004 CBRE reported 608.9 MW of net absorption across its four major Asia-Pacific markets in Q1 2026. Medium SM001
CM005 CBRE described neocloud providers as a prominent Asia-Pacific demand source scaling to support high-performance-computing workloads, while AInvest described DayOne's customers as hyperscale technology firms building AI and cloud infrastructure. Medium SM001, SM003
CM006 CBRE said Asia-Pacific power availability, elevated construction costs, and regulatory complexity continued to extend development timelines in core hubs, and reported major Asia-Pacific market availability down 43% year over year in Q1 2026. Medium SM001
CM007 Channel NewsAsia reported that data centers rely heavily on water to cool servers supporting services including video streaming and AI. Medium SM004
CM008 The Straits Times reported that DayOne had booked 2.3 GW of data-center capacity as of September 20, 2026 and expected to deliver nearly all of it by the end of 2028. High SM002, SM003
CM009 AInvest reported that DayOne had secured 4.6 GW of power resources, booked 2.3 GW, and had 962 MW in service as of September 20, 2026. Medium SM003
CM010 Bloomberg reported on October 21, 2026 that DayOne was weighing a US IPO delay or size cut amid data-center market volatility, according to people familiar with the matter. Medium SM005
CM011 AInvest reported that DayOne uses long-term take-or-pay contracts for customer capacity, but the retained source does not disclose the contracts' duration, price, or utilization. Low SM003
CM012 Startup Fortune reported that DayOne's largest customer represented 69.4% of 2025 revenue and 69.2% of revenue in the first half of 2026. Medium SM006
CM013 ISI Markets reported that DayOne had secured more than 1.5 GW of customer bookings since its 2022 launch as of its August 2026 coverage. Low SM007
CM014 Mission Media's undated article described DayOne as operating more than 500 MW of data-center capacity across seven Asia-Pacific markets and Europe, without stating an as-of date or a comparable capacity denominator. Low SM008
CM015 This analysis defines the addressable market as leased or contracted data-center capacity by location and power, excluding cloud-service revenue, AI applications, hardware sales, and speculative construction spending. Medium SM001, SM003
CM016 The Straits Times placed DayOne in a sector-wide data-center IPO pipeline, and Bloomberg later reported it was considering a delay or smaller US offering amid market volatility. High SM002, SM005
CP001 DayOne announced definitive agreements for a Series C equity financing of more than US$2.0 billion on January 5, 2026. High SP001, SP009
CP002 DayOne's January 2026 company announcement reported approximately 1 GW of secured customer commitments. Medium SP001
CP003 DayOne's January announcement and Data Center Index's profile name the same seven markets: Singapore, Johor, Batam, Bangkok, Tokyo, Hong Kong, and Finland. High SP001, SP002
CP004 Data Center Index tracks two named DayOne campuses and 72 MW across those tracked projects, while stating that its campus coverage is not exhaustive. Medium SP002
CP005 AirTrunk's announcement says its planned JHB3 and JHB4 campuses in Johor would deliver more than 280 MW of IT load combined. Medium SP006
CP006 AirTrunk says its existing JHB1 and JHB2 campuses exceed 420 MW of IT load and are nearly fully contracted. Medium SP006
CP007 TNGlobal reported that AirTrunk secured US$2.325 billion in green project financing for its JHB2 campus. Medium SP005
CP008 AirTrunk announced Johor expansion activity through planned JHB3/JHB4 campuses and a separately financed JHB2 development. Medium SP005, SP006
CP009 Tech Wire Asia reported that Digital Realty's Cyberjaya platform combines two operational facilities and a future development site with an approximately 32 MW IT-capacity target. Medium SP007
CP010 The available provider descriptions distinguish AirTrunk's hyperscale campus build-out, Digital Realty's private-AI and multi-cloud offer, and Equinix's colocation and interconnection products without establishing a performance ranking. High SP005, SP006, SP007, SP008
CP011 Tech Wire Asia reported that Digital Realty planned to bring its ServiceFabric platform to Malaysia in the second half of 2026 subject to licensing approvals. Medium SP007
CP012 Equinix's Johor page lists colocation, Equinix Fabric, and Network Edge and claims 99.999% uptime across its Johor data centers. Medium SP008
CP013 Bloomberg reported on October 21, 2026, citing people familiar with the matter, that DayOne was weighing an IPO delay or a smaller US offering of about US$2.5 billion to US$3 billion amid data-center volatility. Medium SP004
CP014 Bloomberg reported on March 18, 2026, citing people familiar with the matter, that DayOne was seeking to increase an existing loan to as much as US$7 billion. Medium SP003
CP015 Digital Realty's interview describes enterprise-owned private AI cages and hyperscaler shared infrastructure as distinct buyer approaches, but does not provide a comparative cost or customer outcome. Medium SP007
CP016 Comparable list prices, realized rates, and contract terms for the providers in this chapter are not established by the assigned successful source pool. Low
CI001 Light Reading describes DayOne bookings as IT-power capacity committed by clients under legally binding long-term customer contracts. Medium SI001
CI002 Light Reading reports approximately 2.3 GW of DayOne bookings across ten Asia-Pacific and European markets as of its October 2026 report. Medium SI001
CI003 Light Reading reports that seven hyperscale and leading technology customers drive most bookings and that Johor accounts for about 1.4 GW. Medium SI001
CI004 Light Reading reports DayOne revenue of US$512 million for the six months ended June 30, 2026. Medium SI001
CI005 Light Reading reports a DayOne net loss of US$81.9 million for the six months ended June 30, 2026. Medium SI001
CI006 DayOne announced gross Series C proceeds of US$4.5 billion in June 2026. High SI002, SI005
CI007 DayOne said the Series C financing was expected to enable accelerated expansion in its key markets. Medium SI002
CI008 Light Reading reports that DayOne had raised over US$6 billion in equity financing since its 2022 inception. Medium SI001
CI009 Light Reading and The Business Times report that DayOne had filed for a US IPO by October 2026. High SI001, SI004
CI010 Bloomberg and The Business Times report that DayOne was considering an IPO delay or a smaller offering that might raise US$2.5 billion to US$3 billion, with deliberations still ongoing. High SI003, SI004
CI011 ISI Markets reports, without establishing a completed borrowing, that DayOne was said to be negotiating a corporate loan-facility expansion to as much as US$7 billion. Low SI006
CI012 Channel NewsAsia describes water use for cooling as a material operating consideration for Singapore data centers, without reporting DayOne-specific consumption or cost. Medium SI007
CI013 The ICEF Sustainable Data Centers Roadmap describes electricity demand and grid constraints as material data-center issues, without quantifying DayOne's power expense. Medium SI008
CI014 The reviewed public reporting identifies capacity contracts and total revenue but does not quantify DayOne's realized price per kW or MW, discounts, or revenue mix. Medium SI001, SI002
CI015 The assigned sources do not quantify DayOne's customer-acquisition cost, sales-cycle duration, payback, or channel economics. Medium SI001, SI002
CI016 The retained sources do not establish DayOne's gross margin, cash balance, operating cash flow, working capital, capex per delivered MW, or runway. Medium SI001, SI002, SI006
CE001 DayOne describes itself as a Singapore-headquartered platform that develops and operates next-generation data centers for hyperscalers and enterprises. High SE002, SE003
CE002 DayOne's June 2026 release says its campuses are operating or under development across Singapore, Malaysia, Indonesia, Thailand, Japan, Hong Kong, Finland, and Spain. High SE002, SE003, SE004
CE003 DayOne reported more than 1.5 GW of total bookings for capacity since inception in 2022, a bookings metric that does not itself measure commissioned capacity or utilization. High SE003, SE006
CE004 DayOne's July 2025 Singapore facility announcement described SG1 as a 20 MW facility with about 40,000 square meters of gross floor area and Phase One targeted for ready-for-service in 2026. Medium SE004
CE005 DayOne said SG1 would support high-density GPU workloads with hybrid air and liquid cooling, while a separate company release described portfolio-level high-density liquid-cooling-enabled designs. Medium SE001, SE004
CE006 DayOne described on-site solid-oxide fuel-cell power at SG1 as a hydrogen-based proof of concept rather than a demonstrated production system. Medium SE002, SE004
CE007 DayOne described a ten-year power purchase agreement for SG1 backed by bundled renewable-energy certificates sourced locally or through grid-to-grid connections. Medium SE004
CE008 DayOne announced a research and development partnership with the National University of Singapore to explore efficiency and sustainability technologies, including pilot-scale cooling tests in tropical conditions. Medium SE004
CE009 The SG1 announcement said LEED Platinum and BCA Green Mark Platinum certifications would be applied for, which does not establish that SG1 received either certification. Medium SE004
CE010 DataCenters.com lists 11 DayOne data-center locations and identifies LEED ratings for several Johor buildings, but the listing does not establish that every listed location is commissioned. Medium SE002
CE011 Mission Media reports over 500 MW of capacity it says DayOne operates across seven Asia-Pacific markets and Europe, and separately describes 480 MW as operational and under construction plus 590 MW as reserved, without supplying a common date or definition. Medium SE005
CE012 Keppel DC REIT describes its own model as investing in income-producing data-center real estate, illustrating an asset-investment model distinct from DayOne's self-described developer-operator role without establishing DayOne's ownership structure. Medium SE007, SE003
CE013 Princeton Digital Group's competitor-issued portfolio page describes site-level design and capacity details, which is context for asking DayOne for comparable site-level disclosure rather than an independent technical benchmark. Medium SE008
CE014 Bloomberg reported that DayOne was weighing a possible IPO delay or size reduction, while Startup Fortune framed the planned offering as a test of investor appetite for AI infrastructure; these reports indicate capital-timing uncertainty, not a technical failure. Medium SE009, SE010
CE015 The assigned public-source texts do not report measured site uptime, PUE, rack density, cooling performance, or customer-accepted operating results. Medium SE001, SE002, SE003, SE004, SE005, SE006
CE016 DayOne calls its delivery model proprietary and highlights rapid deployment, but the assigned sources do not describe the model's technical components or provide comparative delivery-time evidence. Medium SE001, SE003
CU001 DayOne is described as a wholesale colocation and interconnection operator that provides powered space, cooling, and connectivity while customers install their own computing and network equipment. Medium SU001, SU002, SU006
CU002 The reviewed profiles identify hyperscalers, cloud providers, AI operators, and enterprises as target customer segments, but do not provide a verified DayOne account roster by segment. Medium SU001, SU002, SU006
CU003 YesPress attributes to DayOne a June 2026 statement that customer bookings since its 2022 inception exceeded 1.5 GW, and ISI Markets separately reports more than 1.5 GW of bookings since launch. Medium SU002, SU005
CU004 YesPress reports 1,250 MW of committed and 444 MW of billable IT power as of December 31, 2025. Low SU002
CU005 The reported bookings, committed IT power, and billable IT power are different measures and vintages that the assigned sources do not reconcile into a common customer cohort. Medium SU002, SU005
CU006 Startup Fortune reports that DayOne's largest customer represented 69.4% of 2025 revenue and 69.2% of first-half 2026 revenue; Mukhbir separately reports an approximately 69% first-half revenue share attributed to ByteDance by Reuters. Medium SU003, SU004
CU007 Mukhbir's summary of Reuters Breakingviews attributes 84.3% of DayOne's $512 million first-half 2026 revenue to ByteDance and Oracle combined, without providing Oracle's individual share. Medium SU003
CU008 Startup Fortune says the preliminary prospectus did not name the largest customer, while Mukhbir reports Reuters' secondary attribution of customer names; the assigned evidence therefore does not establish a company-confirmed named customer reference. Medium SU003, SU004, SU001, SU002
CU009 Microsoft's November 2025 announcement described a planned Johor Bahru cloud region, and Oracle's region page lists Malaysia West (Kulai) as live, making public-cloud alternatives visible in Malaysia without establishing DayOne customer overlap. High SU007, SU008
CU010 Oracle lists live public-cloud regions in Batam, Kulai, and Singapore, while Microsoft's 2025 announcement described a planned Johor Bahru region; the disclosures show regional alternatives, not DayOne tenants. High SU007, SU008
CU011 Microsoft's Malaysia announcement names AFFIN Group, PETRONAS, and RHB Bank as Azure users or examples, but those references are not evidence of DayOne customer relationships. Medium SU007
CU012 YesPress describes Singapore, Johor, and Batam as DayOne's regional SIJORI proposition and says customer names are mostly confidential, but it does not establish which named customers use each market or what outcomes they achieve. Medium SU001, SU002
CR001 Bloomberg reported on October 21, 2026 that DayOne was weighing a possible US IPO delay or a smaller offering. Medium SR002
CR002 Earlier 2026 coverage described an approximately US$5 billion IPO target, while Bloomberg later reported a possible US$2.5–3.0 billion offering or delay. High SR002, SR003
CR003 DayOne announced definitive agreements for more than US$2.0 billion of Series C equity financing on January 5, 2026. Medium SR005
CR004 DayOne said it had raised an aggregate US$1.9 billion across its Series A and Series B equity rounds in 2024. Medium SR005
CR005 DayOne said its expansion investments would support approximately 1GW of secured customer commitments. Medium SR005
CR006 DayOne's approximately 1GW of secured customer commitments and ISI Markets' report of more than 1.5GW of bookings since launch in 2022 use different labels and periods and do not establish a comparable customer-level concentration measure. Medium SR004, SR005
CR007 Data Center Dynamics reported DayOne's Singapore SG1 project as a 20MW facility with Phase I scheduled for ready-for-service in 2026. Medium SR001
CR008 Data Center Dynamics reported DayOne received capacity under a Singapore pilot scheme that awarded a combined 80MW to four operators. High SR001, SR007
CR009 Data Center Dynamics reported DayOne signed a 10-year power purchase agreement with Sembcorp backed by bundled renewable energy certificates. Medium SR001
CR010 Data Center Dynamics reported DayOne joined an NUS research partnership exploring cooling needs for tropical data centers. Medium SR001
CR011 Reed Smith reported that Singapore had allocated no new data-center capacity since the 2023 pilot scheme and that new projects face stringent approvals and efficiency standards. High SR007, SR001
CR012 A July 2026 Mahanakorn Partners update described a PUE requirement not exceeding 1.3 before high-efficiency data centers can exercise Thailand BOI corporate-income-tax privileges. Medium SR006
CR013 Data Center Dynamics reported DayOne had recently broken ground on a Thailand site, while Mahanakorn Partners described BOI energy, water, and community considerations; neither source establishes that site's compliance status. Medium SR001, SR006
CR014 DayOne's mechanical-engineer listing hosted by Simplify describes maintenance, vendor coordination, safety responsibilities, and support for 24/7 data-center operations at Lahti. Medium SR008
CR015 ISI Markets reported that DayOne was said to be negotiating expansion of a corporate loan facility to as much as US$7 billion. Low SR004
CR016 DayOne said it secured a mezzanine debt facility of up to €1 billion in 2025 from Brookfield and a sovereign investor. Medium SR005
CV001 ISI Markets reported that DayOne closed its Series C equity financing at US$4.5 billion in gross proceeds in June 2026. Medium SV005
CV002 ISI Markets said neither DayOne nor its investors had put an official number on the company's value, while describing US$20 billion as a reported market estimate. Medium SV005, SV001
CV003 Startup Fortune reported that DayOne was seeking to expand a corporate loan facility to as much as US$7 billion from an existing facility of about US$3.4 billion equivalent. Medium SV001
CV004 InsideASEAN reported that DayOne had filed for a US IPO seeking up to US$5 billion at a projected valuation of around US$20 billion. Medium SV002
CV005 Bloomberg reported on October 21, 2026 that DayOne was weighing a possible IPO delay or a smaller listing raising US$2.5 billion to US$3 billion. Medium SV004
CV006 InsideASEAN reported first-half 2026 DayOne revenue of US$512 million, compared with US$151.5 million in first-half 2025. Medium SV002
CV007 InsideASEAN reported first-half 2026 DayOne net loss of US$81.9 million, compared with US$13.5 million in first-half 2025. Medium SV002
CV008 InsideASEAN quoted the company's prospectus as warning that growth depends significantly on a limited number of global hyperscale customers and diversification may not succeed. Medium SV002
CV009 InsideASEAN reported that two existing DayOne customers had been designated Chinese military companies by the US Department of War, which could affect operations if sanctions or export controls apply. Medium SV002
CV010 InsideASEAN reported that DayOne said it had secured more than 1.5 gigawatts of data-center capacity bookings since 2022. Medium SV002, SV001
CV011 CBRE and the IEA describe power availability as a constraint on where and how quickly data-center capacity can be delivered. High SV008, SV006
CV012 CBRE and the IEA identify infrastructure and approval bottlenecks that can delay data-center expansion despite rising demand. High SV008, SV006
CV013 CompaniesMarketCap listed GDS Holdings' market capitalization as US$4.45 billion as of October 25, 2026. Medium SV007
CV014 Mission Media reported that GDS Holdings retained a 35.6% non-controlling stake in DayOne after the separation. Medium SV003
CV015 Mission Media reported in February 2026 that JPMorgan and Morgan Stanley were selected to lead a proposed US IPO, with Bank of America and Citigroup also participating. Medium SV003
CV016 The assigned reporting does not establish an offer price, share count, or final transaction terms sufficient to calculate an expected investor return. Medium SV002, SV004
Sources
IDPublisherTitleQuote
SO001 Bloomberg Singapore’s DayOne Files for US IPO Joining AI Data Center Rush The data center operator had a net loss of $81.9 million on revenue of $512 million for the six months ended June 30, compared with a net loss of $13.5 million on revenue of $151.5 million in the corresponding period a year earlier, according to its filing Monday with the US Securities and Exchange Commission.
SO002 Startup Fortune DayOne Data Centers Files for Nasdaq IPO Targeting a $20 Billion Valuation DayOne's largest customer accounted for 69.4% of its 2025 revenue and 69.2% of revenue in the first half of 2026, a concentration that FourWeekMBA flagged as a central risk in its read of the prospectus.
SO003 Bloomberg DayOne Said to Weigh Options for IPO After Data Center Rout DayOne Data Centers Ltd. is weighing options for its US initial public offering, including a potential delay or size cut, as volatility around data centers increases, according to people familiar with the matter.
SO004 Mission Media DayOne Data Centers US$5B IPO: Singapore Operator Eyes US$20B Valuation Singapore-based data center operator DayOne Data Centers has selected JPMorgan Chase and Morgan Stanley to lead a US initial public offering expected to raise approximately US$5 billion, with Bank of America and Citigroup also participating in the transaction.
SO005 ISI Markets Singapore's DayOne Data Centers Closes USD 4.5bn Series C, Setting Up Run at USD 20bn IPO The Singapore-headquartered company said it had closed its Series C equity financing at USD 4.5bn in gross proceeds, wrapping up a fundraise that started back in January 2026 with an initial USD 2bn tranche.
SO006 Built In DayOne Data Centers Careers, Perks + Culture Headquartered in Singapore, DayOne’s leadership team draws on over two decades of industry experience and a track record of building Asia's largest data center business.
SO007 The Edge Malaysia Paragon Globe selling Johor land to DayOne Data Centers for RM398m Paragon Globe Bhd (KL:PGLOBE) is selling 26.42 hectares of freehold land in Iskandar Puteri, Johor to DayOne Data Centers Malaysia III Sdn Bhd for RM398.11 million cash.
SO008 Data Center Dynamics DayOne secures $4.5 billion Series C funding The company this week announced the final closing of its Series C equity financing with total gross proceeds of $4.5 billion.
SO009 DayOne Data Centers DayOne | Data Center Company Built For Hyperscale DayOne’s proprietary hub-and-spoke SIJORI (Singapore-Johor-Riau Islands) model creates a first-of-its-kind digital platform — integrating Singapore, Johor (Malaysia) and Batam (Indonesia) into a future-ready regional infrastructure network that simply didn’t exist before.
SO010 Data Center Knowledge DayOne Consolidates Finland Expansion with 560 MW Data Center Development The project is subject to required government approvals and permits.
SM001 CBRE Research Global Data Center Trends 2026 Asia-Pacific inventory increased by 13.4% year-over-year in Q1 across Singapore, Tokyo, Hong Kong and Sydney.
SM002 The Straits Times Singapore’s DayOne files for US IPO joining data centre rush The data centre operator is part of a wave of firms in the sector eyeing IPOs as soon as 2026.
SM003 AInvest DayOne Data Centers: The $20 Billion Bet on Southeast Asia's AI Infrastructure As of September 20, 2026, DayOne had secured resources across 4.6 gigawatts of power capacity, with 2.3 gigawatts already booked by customers and 962 megawatts already in service.
SM004 Channel NewsAsia Semiconductor firms, data centres in Singapore step up efforts to cut water use Data centres, which support services ranging from video streaming to artificial intelligence, also rely heavily on water to keep servers cool.
SM005 Bloomberg DayOne Said to Weigh Options for US IPO After Data Center Rout DayOne Data Centers Ltd. is weighing options for its US initial public offering, including a potential delay or size cut, as volatility around data centers increases, according to people familiar with the matter.
SM006 Startup Fortune DayOne Data Centers Files for Nasdaq IPO Targeting a $20 Billion Valuation - Startup Fortune DayOne's largest customer accounted for 69.4% of its 2025 revenue and 69.2% of revenue in the first half of 2026
SM007 ISI Markets Singapore's DayOne data centers closes USD 4.5bn Series C, setting up run at USD 20bn IPO It says it has locked in more than 1.5 GW of customer bookings since launching in 2022
SM008 Mission Media DayOne Data Centers Taps JPMorgan, Morgan Stanley for US$5B IPO DayOne operates over 500 megawatts of data center capacity across seven Asia-Pacific markets and Europe, including Singapore, Malaysia, Indonesia, Thailand, Hong Kong, Japan, and Finland.
SP001 DayOne Data Centers (press release filed as SEC Exhibit 99.1) DayOne Data Centers Announces Over US$2.0 Billion Series C Financing to Accelerate Global Digital Infrastructure Expansion DayOne Data Centers Limited (“DayOne”), an independent, Singapore-headquartered hyperscale data center platform, today announced that it has entered into definitive agreements for over US$2.0 billion dollar Series C equity financing
SP002 Data Center Index DayOne Data Centers | AI Data Center Pipeline (2026) Data Center Index tracks 2 data center campuses with DayOne Data Centers named as the developer or the tenant. Coverage is named campuses with a published source, not every building.
SP003 Bloomberg Data Center Firm DayOne Seeks to Boost Loan to Record $7 Billion DayOne Data Centers Ltd. is seeking to double the size of an existing loan to as much as $7 billion, according to people familiar with the matter
SP004 Bloomberg DayOne Said to Weigh Options for US IPO After Data Center Rout DayOne Data Centers Ltd. is weighing options for its US initial public offering, including a potential delay or size cut, as volatility around data centers increases, according to people familiar with the matter.
SP005 TNGlobal (AirTrunk announcement) Australia's AirTrunk secures $2.33B green financing for Johor Bahru data center, largest in Malaysia AirTrunk has secured $2.325 billion in green project financing under its Green Financing Framework to support the development of its JHB2 hyperscale data center campus in Johor Bahru, Malaysia.
SP006 Digital News Asia (AirTrunk announcement) AirTrunk doubles down in Malaysia with two new hyperscale campuses in Johor Bahru Located in Iskandar Puteri, Johor, the new campuses—JHB3 and JHB4, will deliver a combined capacity of more than 280 megawatts (MW) of IT load ... The existing JHB1 and JHB2 campuses, with more than 420MW of IT load, are nearly fully contracted and are tracking ahead of investment plans.
SP007 Tech Wire Asia Digital Realty Malaysia is open and already looking beyond Cyberjaya The launch brings together two operational facilities and a future development site, all within roughly 500 metres of each other in Cyberjaya, with a combined target of approximately 32 megawatts (MW) of IT capacity.
SP008 Equinix Johor Data Center Guaranteed 99.999% uptime in all our Johor data centers
SP009 Capacity DayOne Data Centers raises over $2bn to accelerate Europe and Asia expansion DayOne Data Centers has secured more than US$2 billion in Series C equity financing, marking one of the largest private capital raises in the data centre sector in recent years.
SP010 ISI Markets Singapore's DayOne data centers closes USD 4.5bn Series C, setting up run at USD 20bn IPO The Singapore-headquartered company said it had closed its Series C equity financing at USD 4.5bn in gross proceeds, wrapping up a fundraise that started back in January 2026 with an initial USD 2bn tranche.
SI001 Light Reading Singapore's DayOne pursues US listing as its data center footprint grows For the six months ending June 30, the company recorded a net loss of $81.9 million on revenue of $512 million.
SI002 Yahoo Finance, carrying a DayOne Data Centers release distributed by PR Newswire DayOne Data Centers Announces Final Closing of its Series C Equity Financing at US$4.5 Billion DayOne Data Centers Limited ("DayOne"), a Singapore-headquartered global digital infrastructure platform, today announced the final closing of its Series C equity financing with total gross proceeds of US$4.5 billion.
SI003 Bloomberg DayOne Said to Weigh Options for US IPO After Data Center Rout Other options include going ahead with a smaller listing that may raise $2.5 billion to $3 billion, roughly half of what it had originally aimed for, the people said.
SI004 The Business Times DayOne said to weigh options including delay, size cut for US IPO after data-centre rout Other options include going ahead with a smaller listing that may raise US$2.5 billion to US$3 billion, roughly half of what it had originally aimed for, the people said.
SI005 PR Newswire, carrying a DayOne Data Centers release DayOne Data Centers Announces Final Closing of its Series C Equity Financing at US$4.5 Billion The Series C round was led by existing investors Coatue and Hillhouse, now DayOne's two largest shareholders, with participation from notable new investors including the Indonesia Investment Authority (INA) and Achi Capital Partners.
SI006 ISI Markets Singapore's DayOne data centers closes USD 4.5bn Series C, setting up run at USD 20bn IPO DayOne is also said to be negotiating an expansion of its corporate loan facility to as much as USD 7bn, which would make it the largest such borrowing by a data-center operator in Asia.
SI007 Channel NewsAsia Semiconductor firms, data centres in Singapore step up efforts to cut water use Data centres, which support services ranging from video streaming to artificial intelligence, also rely heavily on water to keep servers cool.
SI008 Innovation for Cool Earth Forum Sustainable Data Centers Roadmap Data centers use enormous amounts of electricity, creating challenges for electric grids in many regions.
SE001 Pulse2 DayOne Data Centers Secures Over $2 Billion Series C To Advance Hyperscale Expansion Operationally, DayOne said its portfolio is engineered for next-generation compute requirements. The company highlighted high-density, liquid-cooling–enabled designs, renewable and low-carbon power pathways, and rapid-deployment prefabricated models, supported by utility and government partnerships.
SE002 DataCenters.com DayOne Data Centers | Hyperscale Colocation APAC DayOne builds interconnected data center clusters designed for speed, scale, sustainability, and market access.
SE003 PR Newswire (Yahoo Finance syndication) DayOne Data Centers Announces Final Closing of its Series C Equity Financing at US$4.5 Billion Since its inception in 2022, DayOne has secured more than 1.5 gigawatts (GW) of total bookings for capacity in Asia Pacific and Europe
SE004 The Fast Mode DayOne Breaks Ground on AI-Ready Hyperscale Data Center in Singapore The facility will feature green-powered high-density air-cooled Graphics Processing Unit (GPU) support, hybrid air and liquid cooling technologies.
SE005 Mission Media DayOne Data Centers US$5B IPO: Singapore Operator Eyes US$20B Valuation DayOne operates over 500 megawatts of data center capacity across seven Asia-Pacific markets and Europe
SE006 ISI Markets Singapore's DayOne data centers closes USD 4.5bn Series C, setting up run at USD 20bn IPO It says it has locked in more than 1.5 GW of customer bookings since launching in 2022
SE007 Keppel DC REIT Keppel DC REIT invests in a diversified portfolio of income-producing real estate assets used primarily for data centre purposes
SE008 Princeton Digital Group Where We Operate - Princeton Digital Group JH2 is planned as a five-building campus with a flexible design tailored to support hyperscale cloud and AI infrastructure deployments.
SE009 Bloomberg DayOne Is Said to Weigh Options for US IPO Amid Data Center Rout DayOne Data Centers Ltd. is weighing options for its US initial public offering, including a potential delay or size cut, as volatility around data centers increases
SE010 Startup Fortune DayOne Data Centers Files for Nasdaq IPO Targeting a $20 Billion Valuation - Startup Fortune BofA's Savita Subramanian has warned investors to brace for what she calls an "air pocket" in AI infrastructure spending, arguing that monetization is still unproven and power remains the real bottleneck.
SU001 AI in Asia DayOne's $2 Billion Singapore Bet Is The Real AI | AI in Asia DayOne does not train models. It does not sell GPUs. It sells megawatts, racks, power provisioning, and network connectivity for operators who need to run inference close to Asian users.
SU002 YesPress DayOne Is Turning Three Neighbors Into One Giant Data Center DayOne said in June that bookings since its 2022 inception had passed 1.5 gigawatts.
SU003 Mukhbir DayOne Data Centers IPO 2026: $5 Billion Target The analysis said ByteDance and Oracle together accounted for 84.3% of DayOne’s $512 million first-half revenue in 2026.
SU004 Startup Fortune DayOne Data Centers Files for Nasdaq IPO Targeting a $20 Billion Valuation DayOne's largest customer accounted for 69.4% of its 2025 revenue and 69.2% of revenue in the first half of 2026
SU005 ISI Markets Singapore's DayOne data centers closes USD 4.5bn Series C, setting up run at USD 20bn IPO It says it has locked in more than 1.5 GW of customer bookings since launching in 2022
SU006 Indexed.vc DayOne Data Centers Funding History: $8.4B | Indexed.vc providing carrier-neutral colocation and interconnection solutions to hyperscalers, cloud providers, and enterprise customers.
SU007 Microsoft Microsoft to expand cloud region in Johor Bahru, empowering Southeast Asia's AI Transformation AFFIN Group became the first bank in Asia Pacific to go live with a digital core banking platform running on Microsoft Azure.
SU008 Oracle Public Cloud Regions and Data Centers | Oracle ASEAN Indonesia North (Batam) ... Malaysia West (Kulai) ... Singapore (Singapore)
SR001 Data Center Dynamics DayOne breaks ground on 20MW data center in Singapore Phase I scheduled to be ready-for-service (RFS) in 2026.
SR002 Bloomberg DayOne Said to Weigh Options for IPO After Data Center Rout Other options include going ahead with a smaller listing that may raise $2.5 billion to $3 billion, roughly half of what it had originally aimed for, the people said.
SR003 Mission Media DayOne Data Centers Taps JPMorgan, Morgan Stanley for US$5B IPO Singapore-based data center operator DayOne Data Centers has selected JPMorgan Chase and Morgan Stanley to lead a US initial public offering expected to raise approximately US$5 billion, with Bank of America and Citigroup also participating in the transaction.
SR004 ISI Markets Singapore's DayOne data centers closes USD 4.5bn Series C setting up run at USD 20bn IPO DayOne is also said to be negotiating an expansion of its corporate loan facility to as much as USD 7bn, which would make it the largest such borrowing by a data-center operator in Asia.
SR005 DayOne Data Centers DayOne Announces US$2.0 Billion Series C Financing These investments will strengthen delivery across DayOne’s secured customer commitments of approximately 1GW
SR006 Mahanakorn Partners Data centers in Thailand: BOI incentives meet power, water and clean-energy scrutiny For high-energy-efficiency data centers, the conditions include, among other things, a Power Usage Effectiveness (PUE) requirement not exceeding 1.3 before exercising corporate income tax privileges, minimum IT load, high-speed telecommunications infrastructure, concurrently maintainable systems, continuous-rated engine generators, UPS and cooling redundancy, independent distribution paths, fire protection, 24-hour security, ISO/IEC 27001 certification, a water-management plan, a plan to create benefits for Thailand and Thai workforce requirements for management or specialist positions within a specified period.
SR007 Reed Smith Navigating Singapore’s data centre regulatory framework New projects will be subject to stringent regulatory approval processes and must meet high standards of energy and carbon efficiency, land-use optimisation, and technological innovation.
SR008 DayOne Data Centers (listing hosted by Simplify Jobs) Senior Mechanical Engineer @ DayOne Data Centers Work with engineers, technicians, and the Mechanical Engineering Manager to ensure seamless 24/7 operations.
SV001 Startup Fortune DayOne Data Centers is raising billions before an IPO that could redefine AI infrastructure investing in Asia According to Bloomberg, DayOne is seeking to expand a corporate loan facility to as much as $7 billion
SV002 InsideASEAN DayOne Data Centers Files for US IPO Amid Surge in Data Centre Demand The company noted that its business and growth prospects significantly depend on a limited number of global hyperscale customers, and it may not succeed in diversifying its customer base.
SV003 Mission Media DayOne Data Centers US$5B IPO: Singapore Operator Eyes US$20B Valuation The Shanghai-based parent maintains a 35.6% non-controlling stake in DayOne following the separation
SV004 Bloomberg DayOne Said to Weigh Options for US IPO After Data Center Rout Other options include going ahead with a smaller listing that may raise $2.5 billion to $3 billion, roughly half of what it had originally aimed for
SV005 ISI Markets Singapore’s DayOne data centers closes USD 4.5bn Series C, setting up run at USD 20bn IPO Neither DayOne nor its investors put an official number on what the company is now worth.
SV006 International Energy Agency Data centre electricity use surged in 2025 even with tightening bottlenecks Electricity demand from data centres soared by 17% in 2025, and that of AI-focused data centres climbed even faster – well outpacing growth in global electricity demand of 3%.
SV007 CompaniesMarketCap GDS Holdings market capitalization On Oct 25th, 2026 the market cap of GDS Holdings was reported to be:
SV008 CBRE APAC data centre investment hits record USD11.6 billion as power access reshapes growth Asia Pacific data centre investment reached a record US$11.6 billion in 2025, as power availability increasingly determines where new capacity can be delivered, according to CBRE’s 2026 Asia Pacific Data Centre Trends & Outlook Report.